|
When a liner fails by sliding down a steep slope or
as a result of whales getting entangled in aerator blades, there is often
a great pile of mangled
liner to remove and replace as quickly as possible. Similarly, failed
pipe fusion welds need to be repaired as soon as possible. Often, the
old material is discarded altogether. Then there is an investigation
to determine what happened, often with insurance companies and attorneys
involved, to determine who is at fault. A little forethought can save
much wasted time and money later by removing key samples before tearing
everything out. A tangled mess of liner does not destroy the evidence
of the cause of the failure, but if all the material is removed by bulldozer
or excavator, it just makes the liner features of interest that much
more difficult to find. And in the worst case, one can lose a case as
a result
of prematurely disposing of the evidence.
A 20 mil (0.5 mm) HDPE liner for a decorative pond turned out to be a
16 mil slit film HDPE woven with 2 mil of LLDPE on each surface. It leaked
like a sieve, literally. To ensure there was sufficient water in the
pond for the development's opening (and major sales weekend), the contractor
ripped the liner out, disposed of it, and replaced it with the intended
homogenous HDPE liner. Despite retaining excess unused
material that also leaked like the same sieve, the case brought by the
contractor against the liner supplier/installer was dismissed because
the installed
material was no longer
available; the evidence
had been destroyed.
With appropriate materials science knowledge, it is quite easy to trace
the initiating site(s) of the failure and to recover appropriate samples
for detailed examination if required. The fracture edges and fracture
faces, like the rings of a tree, tell the complete history of the failure
- exactly where it started, at what feature, on which surface or internally,
which way it propagated, how it propagated (fast or slow, steadily or
in steps), then where it transitioned into the large displacement event.
Even if a unique initiation location cannot be identified on site, a
few key samples can be selected that together will tell the complete
story.
With these critical samples preserved, the balance of the unusable material
can then be removed and repairs made.
In one case many years ago, the liner on the whole side slope (200 ft
by 40 ft) of a surface water run-off pond on a hazardous waste site had
shattered by rapid crack propagation (stress cracking), but the initiation
site was quickly traced to a fusion seam that had been "repaired" by
extrusion welding. A sample of the seam was removed for detailed microscope
examination in the laboratory. The precise initiation site was found
on the underside of the weld at a crimp made by overheating - clearly
a combination of a poor material and poor welding.
|
|
| Slow crack growth stress cracking
started at overheating crimp on underside of extrusion-weld-repaired
fusion seam (large arrow), propagated downslope, turned into geomembrane
to left of seam, continued upwards where (small arrows) it bifurcated,
trifurcated, etc., before "shattering" the liner by rapid
crack propagation in a cascading firework pattern along the slope,
into the anchor trench, and under the ice on top of the water (where
I am standing). |
In another case where stress cracking occurred
at extrusion and butt welds in a thick HDPE embedment liner in a mine
facility, the installer
was faulted by the owner and engineer for improper installation. However,
the welds were well made and the material was good. In fact, the liner
manufacturer suggested that a chemical resistance test be performed but
the engineer claimed it was unnecessary. So, a saving of $10,000 resulted
in a multi-million dollar failure. Fortunately, in-situ samples were
taken before the liners were ripped out.
|
|
| In this case, the design engineer
was ultimately faulted for specifying that HDPE be used to contain
a solution with which it was incompatible - the HDPE never stood
a chance. |
In two sewer pipe liner failure projects, one liner
was removed before I was able to get proper samples for the optimum materials
science
examination. In the other case, I was able to enter the sewer pipe
and take samples
before the repairs were made. The second case was much more effectively
presented.
In a very large evaporation pond containing precipitated salts, damage
to the liner was claimed to be slit-type punctures made by large chisels
done as an act of vandalism in the final stages of construction. Under
the microscope it was apparent that the slits were not punctures but
were shear cuts made, in fact, by the precipitate fractured as a result of
the chisel impacts during removal of the precipitate. The contractor
was absolved of responsibility, the damage becoming an operations concern.
If a lined slope fails and tears the liner, examination of the liner's
fracture faces will determine if, perhaps, the liner failed first and
caused the soil to start sliding. Thus, if
the geomembrane, geogrid, geocomposite, high strength geotextile,
or any other geosynthetic fails because it is overloaded, the cause
of failure is not the geosynthetic. However, if the geosynthetic
fails when it is not overloaded; i.e. at stresses below the yield
or break strength of the material, then the geosynthetic may be the
cause of the failure, or may contribute to it.
|
|
| It is more than likely the breaks in the
geogrid would identify the location of initial failure of the wall
and how it progressed, whatever the cause of the failure... |
|
|
| Break in liner before waste slipped. If
edges of break are ductile, the soil-imposed stresses have simply
overloaded the liner; i.e. induced stresses have been higher than
the yield and break stresses of the liner. If edges of break are
brittle, stress cracking has occurred at a stress lower than the
yield stress of the liner. The initiation point and therefore the
cause of the break could easily be identified. If stress cracking
had not occurred, movement of the geomembrane would not have occurred
and the waste may not have slipped catastrophically. This is a very
unique and instructive photograph. The development of this break
was noted and monitored by an in-situ system of leak location electrodes. |
Therefore, as soon as the failure has occurred, call
in a materials performance expert to identify samples that should be
taken and retained
before the
bulk of the geosynthetic is removed and stored or replaced, or repaired.
Even if a few defects require patches, it could be helpful to remove
the flaw before the patch is placed rather than putting the patch
on the
flaw and hiding it.
|
| Broken geonet strands across full width
of geocomposite roll. |
|
|
| Initial failure of this reinforced
floating cover occurred on the upper surface immediately above the
warp reinforcing
yarns under the cyclic stresses caused by wind uplift. |
For more information, please contact Ian
Peggs.
|