|
HDPE - Construction Quality Assurance Plan Chapter 8 |
|
|
8. PROJECT CONTROL: ACTIVITIES, SCHEDULE, AND PROBLEM SOLUTION 8.1 Project Coordination Meetings To guarantee high quality and smooth workflow during installation, clear, open channels of communication are essential. To that end, meetings are critical. 8.1.1 Resolution Meeting Following the completion of the design, plans, specifications, and this CQA Plan for the project, a Resolution meeting will be held. This meeting will include all parties then involved, including the CQA Manager, the Project Manager, the Engineer, the General Contractor, and the Installer. The purpose of this meeting is to begin planning for coordination of tasks, to anticipate any problems which might cause difficulties and delays in construction, and, above all, to present the CQA Plan to all of the parties involved. It is very important that the procedures regarding testing, repair, etc., be known and accepted by all. This site specific CQA Plan may be amended at the Resolution Meeting, after review by the CQA Consultant. The first part of the Resolution Meeting may be devoted to a review of the design drawings and specifications. This is different from the peer review of the design, including design calculations, which would have been carried out previously. This meeting should include all of the following activities:
The meeting will be chaired by the Project Manager and will be documented by a person designated at the beginning of the meeting, or by the CQA Consultant. Minutes will be transmitted to all parties by fax or email within 48 hours, and will be edited and returned to the Project Manager within a further 24 hours. 8.1.2 Pre-Construction Meeting A Pre-Construction Meeting will be held at the site. At a minimum, the meeting will be attended by the Project Manager, the CQA Site Superintendent, the General Contractor, and the Installer. The meeting will be chaired by the Project Manager or designate. Specific requirements for this meeting are to:
8.1.3 Progress Meetings A weekly progress meeting will be held between the Project Manager and the CQA Site Superintendent, the Installer, the General Contractor, and any other concerned parties. The meeting will be chaired by the Project Manager or designate. Minutes will be recorded by the Project Manager or designate. This meeting will discuss current progress, planned activities, revisions to the work, and any new business. The CQA Site Superintendent will log any problems, decisions, or questions arising at this meeting in his/her daily reports. Any matter requiring action which is raised in this meeting will be reported to the appropriate parties. Minutes of the meeting will be circulated to all parties within 24 hours. Corrections must be made and submitted to the Project Manager within a further 24 hours.
The special meeting will be held when, and if, a problem or deficiency has occurred, or is likely to occur that requires special action decisions by several parties. The meeting will be attended by the Project Manager, the CQA Site Superintendent, and other involved parties. If the problem requires a design modification, the Design Engineer should also be present. The purpose of the meeting is to define and resolve the problem or work deficiency as follows:
The meeting will be chaired by the Project Manager and documented by a person designated at the meeting. Minutes will be transmitted to affected parties within 24 hours. Corrections must be made and submitted to the Project Manager within a further 24 hours. 8.2 Project Control Visits Periodically, the construction site will be visited by the CQA Manager. This visit should, if necessary, be coordinated with a similar visit by the Project Manager. Regulatory officials may be informed of the dates of the visits if requested by the Owner, but only by the Project Manager. |
||
Copyright & Disclaimer
Info |