|
HDPE - Construction Quality Assurance Documentation Chapter 3 |
||||||||||||
|
3. PARTIES TO CONSTRUCTION QUALITY ASSURANCE 3.1 Description of the Parties
The Owner owns, and is responsible for, the facility. The Owner is ________________.
The Operator is responsible to the Owner for the operation of the facility. The Operator may be the Owner. The Operator is __________________. 3.1.3 Project Manager The Project Manager is the official representative of the Owner or Operator. In this CQA Plan, the term "Project Manager" will apply equally to "Construction Coordinator" or "Owner's Representative", i.e. the individual in charge of field activities. The Project Manager is __________. 3.1.4 Design Engineer (Engineer) The Engineer is responsible for the design, drawings, plans, and specifications for the HDPE geomembrane and related geosynthetics. In this CQA Plan, the term "Engineer" will refer specifically to the Engineer responsible for the design. The Engineer is __________. 3.1.5 General Contractor/Earthwork Contractor The General Contractor (or the Earthwork Contractor) is responsible for the preparation of the soils relating to the lining system. The General Contractor prepares the subgrade on which the geosynthetics are placed, and the trench in which the geomembrane is anchored. He places the soil cover on top of the geosynthetics, and may place geosynthetics other than the geomembrane. The General Contractor is __________. 3.1.6 Resin Supplier The Resin Supplier produces the raw resin for the Geomembrane Manufacturer. The Resin Supplier is __________. 3.1.7 Geomembrane Manufacturer (Manufacturer) The Geomembrane Manufacturer, or Manufacturer, is responsible for the production of the geomembrane, and, maybe, some prefabricated appurtenance components. The Manufacturer is __________. 3.1.8 Transporter The Transporter transports the geomembrane rolls between the Manufacturer and the site. 3.1.9 Land Surveyor The Land Surveyor performs site surveys to produce the data on which the record drawings are based. The Land Surveyor is __________. 3.1.10 Geomembrane Installer (Installer) The Geomembrane Installer (Installer) is responsible for field handling, storing, placing, seaming, ballasting (loading against wind), and other aspects of the geomembrane (and, perhaps, other geosynthetics) installation. The Installer may also be responsible for transportation of these materials to the site and for the preparation and completion of anchor trenches. The Installer may be a division of the Manufacturer, or a licensed Installer of the Manufacturer's products. The Installer is __________. The Installer's Project Manager is __________. 3.1.11 Construction Quality Assurance Consultant The CQA Consultant is a party, independent from the
Owner, Operator, Manufacturer, Installer, and General Contractor,
that is responsible for observing and documenting activities, and
providing advice related to the CQA of the production, installation,
testing, repair, and covering of the geomembrane lining system. The
CQA Consultant is also responsible for issuing a final CQA report.
The geosynthetics CQA Consultant is __________. 3.1.12 Construction Quality Assurance Laboratory The CQA Laboratory is a party, independent from the Owner, Operator, Manufacturer, Installer, and General Contractor, that is responsible for conducting tests on samples of geomembrane taken from the Manufacturer's plant or from the site and on seam samples taken from the site. The CQA Laboratory may be a division of the CQA Consultant. The CQA Laboratory is __________.
All parties should be qualified to perform their responsibilities and have extensive geosynthetics experience. Specific qualifications will be defined in the Project Specifications. Notwithstanding the Project Specifications, the minimum qualifications of those parties directly associated with the geomembrane will be as follows:
The Manufacturer shall be able to provide sufficient production capacity and qualified personnel to meet the demands of the project. The Manufacturer shall be pre-qualified and approved by the Engineer and the Owner. The qualifications presented by the Manufacturer will, as a minimum, include:
. 3.2.2 Geomembrane Installer The Installer will be trained and qualified to install HDPE geomembranes. The Installer will be approved and/or licensed by the Manufacturer. A copy of the approval letter or license will be submitted by the Installer to the Project Manager. Prior to confirmation of any contractual agreements, the Geomembrane Installer will provide the Project Manager with the following written information:
All personnel performing seaming operations will be qualified by experience. At least one seamer per crew will have experience seaming a minimum of 50,000 m of seams using the same method of seaming proposed for use on this project. The most experienced seamer, the "Master Seamer", will provide direct supervision, as required, over less experienced seamers. The Master Seamer, or his designate with equivalent experience, will be on site whenever seaming is being performed. At least two weeks prior to the start of installation the Installer will provide the Project Manager with a list of proposed seaming personnel and their professional records. This document will be reviewed by the Project Manager and the CQA Consultant. Any proposed seaming personnel deemed insufficiently experienced will not be accepted by the Project Manager or will be requested to pass a seaming test. The Installer will designate one representative as his Site Supervisor who will represent the Installer at all site meetings and be responsible for acting as the Installer's spokesman on site. The Supervisor will be qualified by experience. The Supervisor must have supervised the installation of a minimum of 300,000 m2 of HDPE geomembrane. He will also exhibit good management and communications skills. His appointment will be approved by the Project Manager. The Installer will also designate one representative with responsibility for Quality Control and signing all QC documents. 3.2.3 Transporter All personnel responsible for the loading, transporting, and unloading of the HDPE geomembranes must be fully aware of the consequences of damage to the materials, and must be familiar with handling and transportation constraints required by the Manufacturer. The Transporter will ensure that all rolls of geomembrane are shipped on trailers that can be accessed from the side for safe unloading. The deck of the trailer shall be visually inspected for exposed nails by the Manufacturer before loading. Any such nails shall be removed. 3.2.4 Construction Quality Assurance Consultant The CQA Consultant will be experienced with HDPE geomembranes and be knowledgeable of HDPE geomembrane and seam performance characteristics. The CQA Consultant will be experienced in the preparation of CQA documentation including CQA manuals, forms, reports, and certifications. The CQA Consultant will provide the following, in writing, to the Owner:
3.2.8 Construction Quality Assurance Laboratory The CQA Laboratory will have experience in testing HDPE geomembranes and seams and be familiar with ASTM, NSF, FTMS (include other standards organizations as necessary) and other applicable test standards. The CQA Laboratory will be capable of providing test results within 6 hours of receipt of seam samples and will maintain that standard throughout the project. Copies of valid calibration certificates for all test equipment will be required. The laboratory shall be accredited by ______________________________________________ for those tests included in the Project Specifications and this CQA Plan. The CQA Laboratory shall be approved by the CQA Consultant and the Owner/Project Manager.
The personnel of the CQA Consultant include:
The duties of the CQA Personnel are discussed in the following subsections.
The CQA Manager:
3.3.2 CQA Site Superintendent The CQA Site Superintendent:
The CQA Site Superintendent also:
The duties of the CQA Monitors include, as assigned by the CQA Site Superintendent, monitoring and documenting all appropriate operations. The operations to be monitored by the CQA Monitors include:
The seaming operations to be monitored include:
|
|||||||||||||
Copyright & Disclaimer
Info |