10. GEOMEMBRANE
INSTALLATION
10.1 Earthwork
10.1.1 Surface Preparation
10.1.2 Anchorage System
10.2 Geomembrane Placement
10.2.1 Field Panel Identification
10.2.2 Field Panel Placement
10.2.2.1 Location
10.2.2.2 Compensation for Material Expansion
and Contraction, OR Intimate Subgrade Contact
10.2.2.3 Installation Schedule
10.2.2.4 Weather Conditions
10.2.2.5 Method of Placement
10.2.2.6 Damage
10.3 Field Seaming
10.3.1 Seam Layout
10.3.2 Seaming Equipment and Products
10.3.2.1 Fusion Seaming
10.3.2.2 Extrusion Seaming
10.3.3 Seam Preparation
10.3.4 Weather Conditions for Seaming
10.3.5 Overlapping and Temporary Bonding
10.3.6 Trial Seams
10.3.7 General Seaming Procedure
10.3.8 Nondestructive Seam Continuity Testing
10.3.8.1 Concept
10.3.8.2 Submittals
10.3.8.3 Vacuum Testing
10.3.8.4 Air Pressure Testing
10.3.8.5 Spark Testing
10.3.8.6 Visual Examination
10.3.9 Destructive Testing
10.3.9.1 Concept
10.3.9.2 Location and Frequency
10.3.9.3 Sampling Procedure
10.3.9.4 Size of Samples
10.3.9.5 Field Testing
10.3.9.6 Construction Quality Assurance
Laboratory Testing
10.3.9.7 Installer's Laboratory Testing
10.3.9.8 Destructive Sample Pass/Fail Criteria
10.3.9.9 Procedures if Destructive Sample
Fails
10.4 Defects and Repairs
10.4.1 Identification
10.4.2 Evaluation
10.4.3 Repair Procedures
10.4.4 Verification of Repairs
10.4.5 Large Wrinkles
10.4.6 Bridging of Geomembrane
10.4.7 Geomembrane Anchoring
10.5 Backfilling of Anchor Trench
10.6 Appurtenances
10. GEOMEMBRANE INSTALLATION
10.1 Earthwork
10.1.1 Surface Preparation The Earthwork Contractor
will be responsible for preparing the supporting soil according to the project
specifications. The CQA Consultant will verify that:
a qualified Land Surveyor has established all lines and grades, and
they are approved by the Project Manager;
the supporting soil meets the density specification;
the surface to be lined has been finished so as to be free of irregularities,
protrusions, loose soil, dessication cracks and abrupt changes in grade;
the 50 mm surface layer of the supporting soil does not contain stones
or other objects which may be damaging to the geomembrane; and
there are no areas excessively softened by high water content.
The Installer will certify in writing that the surface on which the geomembrane
will be installed within the next 24 hr is acceptable. The certificate of acceptance
will be given by the Installer to the Project Manager prior to commencement
of geomembrane installation in the area under consideration. The CQA Consultant
will be given a copy of this certificate by the Project Manager. The CQA Consultant
will also acknowledge approval of the subgrade. After the supporting soil has
been accepted by the Installer, it will be the Installer's responsibility to
indicate to the Project Manager any change in the supporting soil condition
that
may require repair work. If the CQA Consultant concurs with the Installer,
then the Project Manager will ensure that the supporting soil is repaired.
10.1.2
Anchor Trenches Anchor trenches will be excavated by the Earthwork Contractor
(unless otherwise specified) to the lines and dimensions shown on the design
drawings, prior to geomembrane placement. The CQA Consultant will verify that
anchor trenches have been constructed according to the design drawings. The edge
of the trench, over which the geomembrane enters the trench, will be rounded
to avoid sharp bends in the geomembrane. There shall be no sharp protrusions
on the inside wall of the trench. No loose soil will be allowed to underlie the
geomembrane in the trenches. Water shall not be allowed to stand, or soften the
soil, in the anchor trench. Responsibility for dewatering of the anchor trench
shall be as agreed upon in the contract or at the Preconstruction Meeting. Backfilling
of anchor trenches will be conducted in accordance with Section 10.5.
10.2
Geomembrane Placement Before any geomembrane is deployed the documents
listed in Appendix B must be received from the Installer and be reviewed
and approved
by the CQA Consultant and Project Manager.
10.2.1 Field Panel Identification A
field panel is a single piece of geomembrane (other than a patch or cap
strip) which is seamed in the field: i.e. a roll or a portion of roll cut
in the
field. It will be the responsibility of the CQA Site Superintendent to
ensure that
each field panel is given an "identification code" (number or
letter-number) consistent with the layout plan. This identification code
will be agreed
upon by the Project Manager, Installer, and CQA Consultant. This field
panel identification
code should be as simple and logical as possible. It will be the responsibility
of the Installer to ensure that each field panel placed is also marked
with the original roll number. The identification code and roll number
will be
marked at a location agreed upon by the Project Manager, Installer, and
CQA Consultant.
Typically, panels will be numbered in the order in which they are placed.
The CQA Site Superintendent will establish a table or chart showing correspondence
between roll numbers and field panel identification codes. The field panel
identification
code will be
used for all CQA records.
10.2.2 Field Panel Placement No geosynthetics
shall be deployed, joined, or tested unless a representative of the CQA
Consultant is present to monitor such activities.
10.2.2.1 Location The
CQA Consultant will verify that field panels and seam orientations are
approximately as
indicated in the Engineer's or Installer's approved layout plan, or as
modified.
It is not practical to expect the field panels to
be laid in exact conformance with the panel layout plan, due to three
dimensional subgrade profiles that cannot be projected on two dimensional
drawings. Thus, it is impossible for the installer to provide a pre-numbered
layout schedule to which he will rigorously adhere.
10.2.2.2 Compensation for Material Expansion and
Contraction
A minimum coefficient of
linear thermal expansion of 1.5 x 10-4°C-1 should be used for
HDPE geomembrane. The actual value will depend on the temperature
range of interest. Actual geomembrane,
not ambient, temperatures must be used to calculate the amount
of compensation required for expansion and contraction. Alternatively,
procedures could be defined that require the geomembrane to be
immediately
covered while in 100% intimate contact with the subgrade.
Unless provided by the designer, as it should be, the Installer will be responsible
for determining the required amount of compensation that must be installed in
the geomembrane to ensure that it will not be unduly tensioned due to temperature
variations in service. Such calculations shall be shown to the CQA Consultant
and Project Manager. The Installer will be responsible for ensuring that sufficient
HDPE geomembrane is installed to compensate for contraction of the material during
anticipated lower temperatures and to prevent expansion and excessive wrinkling
at possible higher covering temperatures.
The latter is clearly very difficult to achieve.
Compensation wrinkles should be small and frequent rather than large
and infrequent. Their performance is a function of flexural modulus
and interface shear strength with the subgrade.
The methods of installing compensation will be discussed with, and approved
by, the Project Manager and the CQA Consultant. The geomembrane must
not be tensioned and must be fully supported by the subgrade when it
is covered by soil or liquid
ballast.
In some countries (e.g. Germany) the geomembrane
must be placed without wrinkles. Installation practices have been
developed to do this. This requires placing complete sections of
the lining system adjacent to one another. However, such practices
can not necessarily be taken and applied to other countries (e.g.
USA) since common US practice is to lay the lining system in complete
individual layers. The procedures for laying the geomembrane should
be outlined in the Project Specifications. The procedure
for wrinkle-free installation is as follows:
Install a suitable section of geomembrane within one day
that has minimal wrinkling.
Cover the geomembrane with cushion geotextile or required
geosynthetic layers.
At the end of the day place cover soil/stone around the periphery
of the deployed area to act as ballast, and to prevent the geomembrane
from contracting during lower overnight temperatures.
When the liner is still somewhat tensioned and flat during
the low morning temperatures, spread the soil/stone across the
flat geomembrane.
Proceed to lay an adjacent section of geomembrane without
wrinkles.
It should be noted that this method of deployment is slower
than a typical North American site, so if specified it will likely
incur a cost premium.If this, or a similar procedure is required
in the Project Specifications, Section 10.2.2.2 of the CQA Plan should
read as follows:
10.2.2.2 Intimate
Subgrade Contact
Note that this section will, if used, replace the previous section
10.2.2.2.
Only that amount of geomembrane will be deployed in one day that can be covered
by other required geosynthetics and the required thickness of cover soil. The
cover soil will initially be placed as ballast around the periphery of that
section of geomembrane. The CQA Consultant will monitor the placement of geomembrane
and soil to confirm that the geomembrane is essentially in complete contact
with
the subgrade at the end of the working day, and is restrained in this position,
without excessive tension, by the peripheral soil. The CQA Consultant will
monitor the spreading of cover soil at the start of the first shift of the
next day to
confirm that no standing or folded wrinkles in the geomembrane are covered
by soil. The geomembrane must be in intimate contact with the subgrade. At
all times
the exposed edges of geosynthetics will be kept clean and protected from damage.
10.2.2.3
Installation Schedule Field panels will be placed one at a time, and
each field panel will be seamed immediately after its placement (in order
to minimize
the number of unseamed field panels exposed to wind). It is beneficial
to "shingle" overlaps
in the downslope direction to facilitate drainage in the event of precipitation,
shingling should also be done in the downstream direction to minimize resistance
to flow. It is also beneficial to proceed downslope and in the direction
of (with) prevailing winds. Scheduling decisions must be made during installation,
in accordance
with varying environmental conditions. In any event, the Installer will
be fully responsible for the decisions made regarding placement procedures.
The
CQA Consultant
will evaluate every change in the schedule proposed by the Installer and
advise the Project Manager on the acceptability of that change. The CQA
Consultant
will verify that the condition of the supporting soil is still satisfactory
for installation
of geomembrane. The CQA Consultant will record the identification code,
roll number, location, weather conditions, and date of installation of
each field
panel.
10.2.2.4 Weather Conditions Geomembrane placement will not
proceed at geomembrane temperatures below -20°C unless approved by the project engineer.
Geomembrane seaming will not proceed at geomembrane temperatures between 0°C
and -20°C or above 75°C unless approved by the Project Manager. Approval
will not be unreasonably withheld provided the Installer can demonstrate the
ability to produce satisfactory seams. The frequency of trial seams, or seam
destructive test sampling, (Section 10.3.6) may be increased at extreme geomembrane
temperatures (<5°C, >75°C). Geomembrane placement will not
be done during any precipitation, in an area of ponded water, or during
excessive winds
except as approved in an Action Decision Meeting. NOTE: The only temperature
of significance is the actual geomembrane temperature, not the ambient
temperature. When exposed to sunlight the geomembrane temperature will
be significantly
higher than ambient.
At low geomembrane temperatures destructive specimens can be
removed from the beginning and end of each seam.
The CQA Consultant will verify that the above conditions
are observed. Additionally, the CQA Consultant will verify that the supporting
soil has not been damaged
by weather conditions. The CQA Site Superintendent will inform the Project
Manager if the above requirements are not observed.
10.2.2.5 Geomembrane Placement The
CQA Consultant will verify that:
equipment used does not damage the geomembrane as a result of handling,
trafficking, excessive heat, leakage of hydrocarbons, or by other means;
any All-Terrain Vehicles (ATVs) used to deploy geosynthetics exert ground
pressures less than 55 kPa (8 psi).
To be practical it should be noted that a 200lb man walking on the liner
will exert a bed of pressure on the liner of about 100 psi (690Pa)!
ATVs are not operated: 1) at excessive speeds, 2) in tight turning circles,
3) under extreme breaking and accelerating conditions, 4) with dirty tires,
and 5) over wrinkles, that might damage the geomembrane.
the prepared surface underlying the geomembrane has not deteriorated
since previous acceptance, and is still acceptable immediately prior to
geomembrane placement;
any geosynthetic elements immediately underlying the geomembrane are
clean and free of debris;
personnel working on the geomembrane do not smoke, do not wear hard-soled
shoes, and do not engage in activities which could damage the geomembrane;
frequently used pathways up and down geomembrane on slopes are protected
by a well-secured roll of geotextile;
the methods used to unroll the panels do not cause excessive scratches
or crimps in the geomembrane and do not damage the supporting soil;
the method used to place the panels minimizes wrinkles (especially differential
wrinkles between adjacent panels);
geomembrane is not allowed to unroll freely down a slope;
geomembrane is not placed under tension, unless approved by the Project
Manager;
adequate temporary loading and/or anchoring (e.g., sand bags, tires),
that does not damage the geomembrane, has been placed to prevent uplift
by wind;
direct contact of equipment with the geomembrane shall not be allowed,
except as previously described for ATVs used to deploy geosynthetics. The
geomembrane shall be protected by geotextiles, extra geomembrane, soil
layers, or suitable materials, in areas where equipment may be used or
traffic may be expected;
only hook bladed utility knives are used to cut through the geomembrane;
appropriate care is to be taken to prevent shock and explosions caused
by static electricity discharges;
all handholds cut for moving panels and damage caused by clamps are
repaired; and
panels are not moved such that subgrade soil can peel the underside
seam flap.
The CQA Site Superintendent will inform the Project Manager if the above requirements
are not observed.
10.2.2.6 Temporary Ballasting Temporary ballasting around
the edges of the installed liner shall be done with sandbags or equivalent
non-damaging ballast material (e.g. tires without reinforcing wires exposed).
Sandbags shall
be handleable by one person and shall be spaced to provide adequate uplift
protection against typical winds that might reasonably be expected to occur
prior to the
addition of adjacent panels or prior to permanent ballasting.
10.2.2.7 Damage The
CQA Consultant will visually examine each panel, after placement and prior
to seaming, for damage. The CQA Site Superintendent will advise the Project
Manager
which panels, or portions of panels, should be rejected or repaired. Damaged
panels or portions of damaged panels, which have been rejected will be marked,
and their removal from the work area recorded by the CQA Consultant. Repairs
will be made according to procedures described in Section 10.4. At a minimum,
the CQA Consultant will ensure that:
each panel is placed in such a manner that it has not been, or is unlikely
to be, damaged; and
any tears, punctures, holes, thin spots, and damaging inclusions, gouges,
and protuberances etc., are marked for repair, or the panel is rejected.
10.3 Field Seaming
10.3.1 Seam Layout Prior to the commencement
of installation activities the Installer will provide the Project Manager and
the CQA Consultant with a proposed panel layout drawing. The CQA Consultant will
review the panel layout drawing and verify that it is consistent with the accepted
state-of-practice and this CQA Plan. No panels may be seamed in the field without
the Project Manager's approval. In addition, panels that significantly change
the layout drawing, (e.g. that change the orientation of seams) shall not be
installed without the Project Manager's prior approval. It is, however, recognized
that such a drawing is only a guide and will, in practice, require modification.
In general, seams should be oriented parallel to the line of maximum slope, i.e.,
oriented up and down, not across, the slope. In corners and other geometrically
complex locations, the number of seams should be minimized. No base seam or tee
seam will be less than 2 m from the toe of slopes, or areas of potential stress
concentrations, unless otherwise authorized by the Project Manager.
If roll end seams are unavoidable on slopes, the upslope panel shall overlap
the downslope panel and adjacent panel cross-seams shall be staggered by at least
2 m. A seam numbering system compatible with the panel numbering system will
be agreed upon at the Resolution or Preconstruction Meeting. Seams are usually
identified by the panel numbers on each side, e.g. seam 1 / 2, for the seam between
panels 1 and 2.
10.3.2 Seaming Equipment and Products Approved methods for field seaming
are thermal fusion (hot wedge, hot air, or combination) seaming and extrusion
seaming. Proposed alternate methods will be documented and submitted
to the Project Manager and CQA Consultant for approval. Only apparatus that
has been specifically
approved by make and model will be used. The Installer will use appropriate
measuring equipment to ensure that required temperatures are being achieved.
A combination of hot wedge and hot air probably
produces the most durable seam. Ultrasonic and electrofusion seaming methods
are also available, but are not yet well established.
The Project Manager will submit all documentation to the CQA Consultant for his
concurrence.
10.3.2.1 Fusion Seaming Fusion seaming must be done with
automated self-propelled machines. The fusion seaming machines will be equipped
with gauges giving hot wedge temperatures geomembrane temperature, wedge.
Temperature, speed, and nip roll pressure settings will be verified by the
Installer prior
to each seaming period. Nip roll and wedge geometries shall be such as to
minimize residual stresses at the edge of the seam, i.e. to minimize reduction
in stress
cracking resistance of the geomembrane. The CQA Consultant will log ambient
conditions, geomembrane temperatures, seaming apparatus temperatures and speeds,
equipment
serial number, and operator initials. The CQA Consultant will also verify
that:
the Installer maintains on-site the number of operable seaming machines
decided at the Resolution Meeting;
equipment used for seaming does not damage the geomembrane;
for tee seam intersections, all edge flaps are cut back to the edge
of the outermost peel-tested track of the seam prior to seaming;
electric generators and fuel containers are placed on a smooth protective
layer such that no damage occurs to the geomembrane;
a smooth insulating plate or fabric is placed beneath the hot seaming
apparatus after usage;
the geomembrane is protected from damage in heavily-trafficked areas;
and
build-up of moisture between the sheets is prevented. To accomplish
this a movable protective layer may be used directly below each overlap
of geomembrane that is to be seamed.
10.3.2.2 Extrusion Seaming Extrusion-seaming apparatus will be equipped
with gauges giving the relevant temperatures of the apparatus such as the temperatures
of the extrudate, nozzle, and preheat air. The Installer will provide documentation
(including QC certificates) regarding the welding rod or resin pellets to the
Project Manager and the CQA Consultant, that show that the resin is the same
HDPE resin as the geomembrane itself order a Melt Index that is compatable with
the geomembrane. Other welding rod resins must be approved by the Project Manager
and the CQA Consultant. The CQA Consultant will log apparatus temperatures, extrudate
temperatures, ambient conditions, and geomembrane temperatures at appropriate
intervals. The CQA Consultant will verify that:
the Installer maintains on-site the number of operable seaming machines
decided at the Resolution Meeting;
equipment used for seaming will not damage the geomembrane;
the extruder is purged prior to seaming until all heat-degraded extrudate
has been removed from the barrel;
feed resin is maintained clean and dry;
the electric generator and fuel containers are placed on a smooth intermediate
layer such that no damage occurs to the geomembrane;
a smooth insulating plate or fabric is placed beneath the hot seaming
apparatus after usage; and
the geomembrane is protected from damage in heavily trafficked areas.
10.3.3 Seam Preparation The CQA Consultant will verify that:
prior to seaming, the seam area is clean and free of moisture, dust,
dirt, debris of any kind, foreign material, and any mechanical damage;
if seam overlap grinding is required, the process is completed according
to the Manufacturer's instructions but within 30 minutes of the seaming
operation, and in a way that does not damage the geomembrane;
the abrading does not remove more than 10 percent of the thickness of
the geomembrane, and the resulting abrasion marks are covered by the finished
extrusion bead;
any visible abrasion marks, after seaming, are essentially perpendicular
to the direction of the seam;
the abrading does not introduce damaging gouges in the geomembrane;
and
seams/panels are aligned with a minimum of wrinkles
and "fishmouths".
10.3.4 Weather Conditions for Seaming The following
protocols will be observed during seaming:
Unless authorized in writing by the Project Manager,
no seaming will be attempted at geomembrane temperatures below -0°C or above 75°C.
Below a geomembrane temperature of 5°C, the
need for pre-heating and additional testing should be discussed with
the Project Manager and
CQA Consultant.
In all cases, the geomembrane in the seaming area will be dry and protected
from wind and airborne particulates, especially bentonite powder.
Geomembrane temperatures will be measured with a surface temperature
thermocouple or a calibrated infrared pyrometer.
If the Installer wishes to use methods which may
allow seaming at geomembrane temperatures below 0°C or above 75°C, the Installer will demonstrate
(by testing trial seams) that such methods produce seams which are entirely equivalent
to seams produced at geomembrane temperatures above 0°C and below 75°C,
and that the overall quality of the seam and durability of the geomembrane
are not adversely affected. In addition, the Installer will prepare written
certification
that states that the seaming procedure does not cause any physical or mechanical
modification to the geomembrane that will generate any short or long-term
damage to the geomembrane liner. The CQA Consultant will verify that these
requirements
are observed and will advise the Project Manager if potential problems are
perceived. The Project Manager will then decide if the seaming will be stopped
or postponed.
Such decisions may be the subject of an Action Decision Meeting.
10.3.5 Overlapping
and Temporary Bonding The CQA Consultant will verify that:
It may be necessary to carefully remove this top flap to prevent
ice attaching to it.
no solvent or adhesive is used unless the product is approved in writing
by the Project Manager (samples must be submitted to the Owner for testing
and evaluation);
any procedure used to temporarily bond adjacent
panels together does not damage the geomembrane. In particular, the temperature
of hot air at
the nozzle of any spot seaming apparatus will be controlled such that the
geomembrane is not damaged. "Damage" includes a loss in durability;
and
Spot "tack" welds
at low ambient temperatures have been seen to initiate stress cracks
around the heated area.
It is preferable that tack welding not be done.
temporary bonds do not interfere with the ability to perform shear and
peel tests on the actual production seam.
The CQA Consultant will log all relevant temperatures and conditions, and
will log and report any non-compliance to the Project Manager. If protective
layers of geomembrane are placed on the barrier layer geomembrane for any
purpose (e.g.
puncture protection in drainage trenches), they shall not be tack or spot
welded to the barrier layer. They shall be fully welded, except for a small
pressure
relief segment, along the complete periphery of the protective layer or they
shall not be welded at all.
Differential contraction effects have caused several barrier
layers to be torn at tack welds holding protective layers in place.
Sacrificial geomembrane layers will interfere with the ability to
locate leaks in the liner by geoelectric methods should such testing
be ultimately required. It is far preferable to use geotextile for
protection purposes.
10.3.6 Trial Seams Trial seams will be made
by each machine/operator combination on strips of HDPE geomembrane to verify
that seaming can be successfully
performed. Such trial seams will be made at the beginning of each seaming
period (i.e., at the beginning and middle of each working shift), but at
least once
every four hours, for each seaming apparatus/operator combination used in
the seaming period. In addition, a new trial seam will be conducted when
a welding
apparatus has been restarted after being switched off. A trial seam will
also be made in the event that the geomembrane temperature changes more than
25°C
since the last passing trial seam. Trial seams will be made under the same conditions
as production seams will be made e.q. or soil, GCL, on slopes, or walls, as appropiate.
When geomembrane temperatures are below 5°C or higher than 75°C more
frequent trial seams may be required. In general, trial seams will be conducted
as follows: The trial seam sample will be at least 1.5 m long by 0.3 m wide
with the seam centered lengthwise. Seam overlap will be as indicated in Section
10.3.5.
The CQA Consultant will observe all trial seam procedures. Four specimens,
each 25 mm wide and a minimum of 150 mm long, will be cut from the center
section
of the trial seam sample by the Installer. Two specimens will be tested in
shear and two in peel using a calibrated field tensiometer. They should meet
project
specifications. If any specimen fails, the entire operation will be repeated.
If the second trial seam fails, the seaming apparatus and seamer will not
be approved for production seaming until the deficiencies are corrected and
two
consecutive successful trial seams are achieved. The remainder of the successful
trial seam sample will be assigned a number and marked accordingly by the
CQA Consultant, who will also log the date, time, geomembrane temperature,
number
of seaming unit, settings, name of seamer, and pass or fail description.
The remainder of the sample will be cut into two pieces, one each to be retained
by the Owner, and Installer. A trial seam shall also be prepared by each
seaming
machine/operator at the completion of seaming each day to determine whether
changes in seam quality might have occurred during the last part of the seaming
period.
Alternatively, a seam destructive sample could be required
at the end of the day.
10.3.7 General Seaming Procedure Unless otherwise specified, the general
seaming procedure used by the Installer will be as follows:
For fusion seaming, a movable protective layer of plastic may be placed
directly below each overlap of geomembrane that is to be seamed. This is
to help prevent any moisture build-up between the sheets to be seamed.
If required, a firm substrate may be provided by using a flat board,
or other similar hard surface placed directly under the seam overlap.
Fishmouths or wrinkles at the seam overlaps will be cut along the peak
of the wrinkle in order to achieve a flat overlap. The cut fishmouths or
wrinkles will be seamed and any portion where the overlap is inadequate
will then be patched with an oval or round patch of the same geomembrane
material extending a minimum of 150 mm beyond the cut in all directions.
The end of the cut should be rounded.
If seaming operations are carried out at night, adequate illumination
will be provided.
Seaming will extend to the outside edge of panels placed in the anchor
trench.
Each seam will be labelled with the seaming machine number, the operator's
initials, machine temperature and speed settings, date, time, and direction
seamed. The
CQA Consultant will monitor the above seaming procedures, and will inform the
Project Manager of any unsatisfactory deviations from standard practice.
10.3.8
Nondestructive Seam Continuity Testing
10.3.8.1 Concept The Installer
will nondestructively test all field seams over their full length using a
vacuum test unit, air pressure test (for double fusion seams only), spark
test, or other
approved method. Vacuum testing, air pressure testing, and spark testing
are described in Sections 10.3.8.3, 10.3.8.4, and 10.3.8.5 respectively).
The purpose
of nondestructive testing is to check the continuity of seams. It does not
provide any information on seam strength. Continuity testing will be carried
out as the
seaming work progresses, not at the completion of all field seaming. Nondestructive
testing will not be permitted unless there is, in the opinion of the CQA
Consultant, adequate illumination. The CQA Consultant will:
observe all nondestructive testing;
record location, date, test unit number, operator, and outcome of all
testing; and
log and inform the Installer and Project Manager of any required repairs.
The Installer will complete any required repairs in accordance with Section
10.4. The
CQA Consultant will:
The following procedures will apply to segments of seams that cannot be nondestructively
tested:
All such seam segments will be cap-stripped with the same type of geomembrane
material, or
All such seam segments will be very carefully prepared and welded by
the master seamer under the observation of the consultant.
If the seam is accessible to testing equipment prior to final installation
(e.g. after prefabrication), the seam will be nondestructively tested prior
to final installation.
For instance, prefabricated pipe boot seams can be tested hydrostatically.
The seaming and cap-stripping operations must be observed for proper
procedures by the CQA Consultant and Installer's QC representative.
All extrusion seams can be spark tested if a conductive wire
is installed at the triple point of the seam (under edge of top sheet)
and grounded prior to seaming.
The installer will write the details of each seam nondestructive test on the
geomembrane. For air pressure tests this will include the initials of the tester,
the date, start time and pressure, end time and pressure, and pass or fail result.
For vacuum testing this will include the initials of the tester, the date, and
pass or fail result. For spark testing this will include the initials of the
tester, the date, voltage setting, and pass or fail result. When a test fails,
the number of the appropriate repair will also be recorded on the geomembrane.
10.3.8.2
Submittals Prior to any nondestructive testing, the Installer shall
submit to the Owner and CQA Consultant calibration certificates for
all pressure gages
to be used during vacuum and air pressure testing, or shall otherwise
demonstrate that all gages are in satisfactory working condition.
10.3.8.3 Vacuum Box
Testing (ASTM D5641) The equipment will be comprised of the following:
a vacuum box assembly consisting of a rigid housing, a transparent viewing
window, a soft neoprene gasket attached to the bottom, port hole, valve
assembly, and a vacuum gauge;
a vacuum tank and pump assembly equipped with a pressure controller
and pipe connections;
a pressure/vacuum hose with fittings and connections;
a soapy solution that does not cause environmental stress cracking in
the geomembrane, and
a soap solution applicator.
The following procedure will be followed:
for fusion seams (not normally tested with a vacuum box), cut off the
free flap with an approved cutter (so that the lower geomembrane is not
damaged) prior to testing the seam;
energize the vacuum pump and reduce the tank pressure to approximately
5 kPa gauge;
with a soapy solution, wet a strip of geomembrane which is wider and
longer than the vacuum box;
place the box over the wetted area;
close the pressure relief valve and open the vacuum valve;
ensure that a leak-tight seal is created;
examine the geomembrane seam through the viewing window for the presence
of soap bubbles (large bubbles, or fine froth) for a period of not less
than 5 seconds;
if no bubbles or foam appear after 5 seconds, close the vacuum valve
and open the pressure relief valve. Move the box over to the adjoining
section of seam, with some overlap, and repeat the process;
all areas where soap bubbles appear will be marked and repaired in accordance
with Section 10.4.3; and
excess soap solution shall be cleaned or rinsed off the geomembrane
and seam.
10.3.8.4 Air Pressure Testing (ASTM D5820) The following procedures are
applicable to those seaming processes which produce a double track seam with
a central channel. The equipment will be comprised of the following:
an air pump equipped with a pressure gauge capable of generating and
sustaining a pressure between 160 and 280 kPa mounted on a cushion to protect
the geomembrane;
a pressure hose with fittings and connections;
a sharp hollow needle, or other approved pressure-feed device attached
to a pressure gage; and
clamps or other devices to seal the ends of the seam to be tested.
The following procedures will be followed:
seal both ends of the seam to be tested;
insert the pressure-feed device into the channel of the seam;
energize the air pump to a pressure between 165 and 275 kPa (depending
on geomembrane thickness) as indicated in Table 2, close the valve, and
allow the temperature of the air in the channel, and thus the pressure,
to stabilize for about 2 minutes;
TABLE 2. AIR CHANNEL TEST PRESSURES FOR HDPE GEOMEMBRANES
Geomembrane Thickness
Minimum Pressure
Maximum Pressure
(mm)
(in.)
(kPa)
(psi)
(kPa)
(psi)
1.0
0.040
165
24
240
35
1.5
0.060
185
27
275
40
>2.0
>0.080
205
30
275
40
verify that the stabilized pressure is within the required range and
note the pressure loss after a further 5 minutes. If loss of pressure exceeds
the amount indicated in Table 3, or if the pressure does not stabilize,
locate the faulty area and repair it in accordance with Section 10.4.3.
TABLE 3. ALLOWABLE PRESSURE LOSS IN AIR CHANNEL TEST
Geomembrane Thickness
Minimum Pressure Drop
(mm)
(in.)
(kPa)
(psi)
1
0.040
28
4.0
1.5
0.060
21
3.0
>2.0
>0.080
14
2.0
verify that the full length of the seam section has been tested by observing
the air pressure gauge for a decrease in pressure when the seal at the
end of the channel away from the air pump is removed. If there is a blockage
in the channel, the entire seam must be capped, with cap seams being nondestructively
tested, or the location of the blockage must be found and the untested
part of the seam must be properly tested; and
remove the needle or other approved pressure-feed device and seal the
hole.
Note that a decrease in the geomembrane temperature (e.g. due to clouds) will
also cause a reduction in air channel pressure.
It can be quite difficult to achieve a seal around a needle at
low geomembrane temperatures. Installers use many different techniques
to achieve a proper seal.
10.3.8.5 Spark Testing (ASTM D6365) There are two types of spark testing
equipment - AC and DC. The ASTM D6365 standard is written for DC equipment, which
often uses a metal brush for the search electrode. The AC equipment is typically
a hand held unit with a rounded tip probe. Spark Testing is frequently used on
short, detail (sump, penetration) extrusion welds that cannot be tested by vacuum
box testing, it is used on cost-in liner welds. Occasionally it is used on long
extrusion seams as the primary nondestructive test method. The same general test
method can also be applied to the geomembrane panels themselves when they are
manufactured with an electrically conductive bottom surface layer. For seams,
a copper wire or tape is placed within the geomembrane overlap, just to the inside
of the center of the extruded bead. The wire is exposed at one end of the seam
or it is buried in the conductive subgrade.
Prior to testing, a trial calibration seam must be made to confirm the
minimum voltage required to discharge across a hole in the seam between
the search electrode and the copper wire.
The test procedure is as
follows:
DC equipment connect the negative (ground) electrode
of the testing equipment to the exposed end of the copper wire, or to
a grounding rod if the copper
wire is buried in the subgrade.
Calibrate using a seam with a known leak path of the largest reached
distance
Connect the positive electrode to the wire brush or other type of search
electrode.
Clean all debris and moisture from the seam area.
Apply a potential difference of between 20 and 55 kVDC, as determined
in the calibration test, between the electrodes. Table 4 D6365 recommends
the DC voltage to be used for different lengths of leak passages based
on the following equation:
V =kd 0.5
Where V= Applied Voltage (s)
K= Constant, 7900
D= Distance to test (mm)
Table 4.
Typical example of required voltage settings :
The distance to test is typically not the thickness of the geomembrane
but the distance from the edge of the extrusion bead to the copper
wire.
Sweep the search electrode over the surface of the seam, maintaining
contact with the extruded bead and the top of the lower geomembrane at
the edge of the bead.
Monitor for audible and/or visible spark discharges that are indicative
of a defect. Mark defects for repair.
Care must be taken when spark testing almost completed landfill caps - a spark
can cause a small landfill gas explosion.
Spark testing must not be performed when the liner is wet. It should
be recognized that this test requires no signal be generated for a passing
result. There are
many conditions in addition to adequate seaming under which no signal will
be generated: proper connections may not be made, the voltage may be
set
too low,
the search electrode may be held too far away. Periodic calibration should
be performed.
10.3.8.6 Visual Examination Air pressure, vacuum box, and spark testing
methods apply only to seams. Installer and CQA personnel shall continuously visually
examine the geomembrane panels for the presence of other penetrating and nonpenetrating
defects and shall continuously feel for protuberances when walking on the geomembrane.
Visual examination should take advantage of low angles of sunlight and early
morning condensation on the geomembrane. As a final shape of CQA the Project
Engineer reserves the right to require an electrical, or other type of nondestructive
liner integrity (leak location) survey to be performed on the complete lining
system. A separate specification document is needed for such surveys.
It may be appropriate to require an electrical method of testing
the complete geomembrane for holes, not just the seams as required
above. There are several mobile and in-situ systems that can identify
and locate leaks in soil-covered, water covered, and uncovered liners.
In-situ systems monitor the liner integrity very quickly and quickly
confirm when repairs have successfully been made. It is better to
perform this test when the cover soil has been placed on the geomembrane,
to identify damage caused by the soil's placement.
10.3.9 Destructive Testing
10.3.9.1 Concept Destructive seam tests
will be performed at selected locations. The purpose of these tests is to evaluate
seam bond strength and the effects of seaming on the adjacent geomembrane. Seam
strength testing will be done as the seaming work progresses, not at the completion
of seaming.
10.3.9.2 Location and Frequency The CQA Site Superintendent
will select locations where seam samples will be cut out for laboratory
testing. Those locations will be established as follows:
A minimum frequency of one sample for every 150 m of seam made by each
extrusion machine/operator combination and each fusion machine each day
- unless a different frequency is stated in the project specifications.
Conditions under which testing frequency may be increased or decreased
as the project progresses will be agreed upon by the Installer, Project
Manager, and CQA Manager at the Resolution or Preconstruction Meeting.
Such conditions may be as described in the Method of Attributes, GRS.GM
14.
Test locations will be determined during seaming at the CQA Site Superintendent's
discretion. Selection of such locations may be prompted by suspicion of
overheating, contamination, offset seams, or any other evidence of imperfect
seaming.
If trial seams are not made at the end of the day one sample for destructive
testing shall be removed from the last seam made by each seaming machine
at the end of each working day.
The Installer will not be informed in advance of the locations where the
seam samples will be taken. Test frequencies may be increased or decreased
at the CQA Site Superintendent's discretion depending on the consistency
of the test
results.
In critical installations it may be appropriate to take seams
from the anchor trench or other strategic (non-critical) locations.
However, this will not randomly spot check the quality of the seamer's
work product.
10.3.9.3 Sampling Procedure Samples will be cut by
the Installer as the seaming progresses in order to have laboratory test
results before the geomembrane
is covered by another material. The CQA Consultant will:
observe sample cutting;
assign a number to each sample, and mark it accordingly; and
record the sample location on the layout drawing.
All holes in the geomembrane resulting from destructive sample removal will be
immediately repaired in accordance with repair procedures described in Section
10.4.3. The continuity of the new seams in the repaired area will be tested according
to Section 10.3.8.
10.3.9.4 Size of Samples At a given sampling location,
two types of samples will be taken by the Installer. First, two pairs
of specimens for field peel and shear testing will be taken. Each of these
specimens will
be 25 mm wide by at least 150 mm long, with the seam centered across
the width. The distance between these two pairs of specimens will be 1.1
m. If both pairs
of specimens pass the field tests described in Section 10.3.9.5, a sample
for laboratory testing will be taken. The sample for laboratory testing
will be located
between the two pairs of specimens taken for field testing. Unless determined
otherwise at the Preconstruction Meeting, or in the Project Specifications,
the destructive sample will be 0.3 m wide by 1.1 m long with the seam centered
lengthwise.
The sample will be cut into three parts and distributed as follows:
one portion, measuring 0.3 m x 0.3 m, to the Installer for QC laboratory
testing;
one portion, measuring 0.3 m x 0.3 m, to the Owner for archive storage;
and
one portion, measuring 0.3 m x 0.5 m, to the CQA Consultant for CQA
Laboratory testing.
10.3.9.5 Field Testing The four 25 mm wide specimens mentioned in Section
10.3.9.4 will be tested in the field, by calibrated gaged tensiometer, one of
each pair in peel and one in shear. If any field test specimen fails to pass
the criteria of Table 4 and the project specifications, then the procedures outlined
in Section 10.3.9.9 will be followed. The CQA Consultant will witness all field
tests and mark all samples and portions with their unique sample number. The
CQA Consultant will also log the date and time of sampling, and test pass or
fail description. If the two pairs of specimens meet the project specifications,
the sample qualifies for testing in the laboratory; if they fail, the seam should
be repaired in accordance with section 10.4.3.
10.3.9.6 Construction Quality
Assurance Laboratory Testing Destructive test samples will be packaged
and shipped to the CQA laboratory by the CQA Consultant, in a manner
which will not
damage the test sample. The Project Manager will verify that packaging
and shipping conditions are acceptable. The Project Manager will be responsible
for storing
the archive samples. This procedure will be fully outlined at the Resolution
Meeting. Test samples will be tested by the CQA Laboratory. Testing will
follow ASTM D6392, but with no requirement for sample conditioning time.
The minimum
acceptable values to be obtained in these tests are those indicated in
the specifications or as shown in Table 5. Five specimens will be tested
in peel and five in shear.
Specimens will be selected alternately by test from the samples (e.g.,
peel, shear, peel, shear, etc.). The CQA Laboratory will provide test
results no more
than 6 hours after they receive the samples. The CQA Site Superintendent
will review laboratory test results as soon as they become available,
and make appropriate
recommendations to the Project Manager.
10.3.9.7 Installer's Laboratory Testing The Installer's laboratory
test results will be available to the Project Manager and the CQA Consultant
for review.
10.3.9.8
Destructive Sample Pass/Fail Criteria The criteria shown in Table
5, or the requirements of the project specifications (whichever are
the more comprehensive)
must be met for the acceptance of peel and shear test specimens: TABLE 4 IN
CQA PLAN
TABLE 5. SEAM
SPECIMEN TEST (ASTM D4437) SPECIFICATIONS
PARAMETER
CRITERIA
Peel Strength
>70% (fusion seam), >65%
(extrusion seam) minimum specified* geomembrane yield strength
Real Separation
zero
BREAK LOCATION
OUTSIDE THE WALL
Shear Stength
>95% minimum specified* geomembrane
yield strength
Shear Elongation
>100% of distance between
edge of seam and nearer grip
Break Location
Outside the weld
* The yield strength specified by the Manufacturer, which is usually the population
average value less 2 standard deviations.
There is, in fact, little technical significance to the determination
of seam shear strength and peel strength due to the large area of
the shear interface. The seam bond strength will have to be less
than about 20% of maximum bond strength for the seam to fail before
the geomembrane breaks. However, these strength parameters are retained
in the seam specifications since regulators will likely not accept
specifications without them.
The inclusion of seam peel separation and shear elongation parameters
provides some indication of the durability of the seam. Shear elongation
indicates if damage to the geomembrane has occurred during seaming.
This is extremely important. If seam separation can occur during
the application of peel stresses (as can occur in the field) there
may be a decrease in stress rupture resistance of the geomembrane.
The peel criteria apply to both tracks of double track seams. Nine out of the
ten specimens in a seam destructive sample must meet the criteria above for acceptance
of the complete destructive sample.
Other sample acceptance criteria allow 1 peel and 1 shear specimen
failure, but not 2 peel, or 2 shear failures. Alternatively, 1 failure
is allowed (for each of peel and shear) provided the average values
of all five specimens meet the strength criterion. However, the failing
specimen must exceed 80% of the specified strength. Note that it
is not difficult for good installers to make seams in which all the
specimens pass, and good installers will require 10 passing specimens
in their QC programs.
The CQA Consultant will ensure that the CQA Laboratory retains all sample and
specimen remnants, clearly labelled, for at least 30 days after the last specimen
for the project has been tested.
10.3.9.9 Procedures if Destructive Sample
Fails The following procedures will apply whenever a sample fails a destructive
test, whether that test is conducted by the CQA Laboratory, the Installer's
laboratory, or on the field tensiometer. The Installer has two options:
Reconstruct the seam between the nearest passing destructive test locations
on each side of the failed sample; or
Trace the seaming path to an intermediate location (3 m minimum from
the failed test location in each direction) and take a small sample for
an additional field test at each location. If these additional samples
pass tensiometer testing, then full destructive test samples should be
taken. If these laboratory destructive test samples pass the tests, then
the seam should be reconstructed between these locations by capping. If
either sample fails, then the process is repeated to establish the zone
in which the seam should be reconstructed.
If a fusion-type seam fails destructive testing and the Installer chooses to
repair the seam, the only acceptable repair method is as described in Section
10.4.3.
Only seams bounded by two locations from which samples passing laboratory destructive
tests have been taken will be considered acceptable. An additional destructive
test sample will be taken from repair seams when the length of a reconstructed
seam exceeds 50 m. This sample must pass destructive testing or the procedure
outlined in this section must be repeated. The CQA Consultant will document
all actions taken in conjunction with destructive test failures.
10.4 Defects
and Repairs
10.4.1 Identification All seams and non-seam areas
of the geomembrane will be examined by the Installer and the CQA Consultant
for
identification of defects, protruding and penetrating objects, lack of subgrade
support, overheating, overgrinding, holes, blisters, undispersed raw materials,
scratches and gouges, and any sign of contamination by foreign matter. To
facilitate the examination the geomembrane surface will be kept clean by
the Installer (or
as agreed at the Preconstruction Meeting).
The use of electrically conductive and white surfaced geomembrane
will facilitate the location of holes and defects in geomembranes
away from seams.
10.4.2 Evaluation Each suspect location, both in seam and non-seam areas,
will be nondestructively tested using an appropriate method, such as vacuum box
testing. Additional methods, such as electrical methods and infrared thermography,
may also be used. Each location which fails the nondestructive testing will be
marked by the CQA Consultant and repaired by the Installer. Work will not proceed
with any materials which will cover locations that have been repaired until passing
destructive and nondestructive test results have been obtained on the repairs.
10.4.3 Repair Procedures Any portion of the geomembrane exhibiting
a flaw, or failing a destructive or nondestructive test, will be repaired.
Several procedures
exist for the repair of these areas. The final decision as to the appropriate
repair procedure will be agreed upon between the Project Manager, Installer,
and CQA Manager at the Preconstruction Meeting or at an Action Decision Meeting.
The procedures available include:
patching, used to repair all penetrating holes, tears, undispersed raw
materials, and contamination by foreign matter;
Small holes (pinholes) will not be filled by an
extruded bead repair. The remaining pit in the bottom surface can
act as a stress concentrator. The spot heating at that location may
further aggravate the potential for cracking. Therefore, all penetrating
holes should be patched.
spot beading, used to repair small surface scratches, or other minor,
localized nonpenetrating flaws; and
capping with a strip of geomembrane, used to repair long lengths of
failed seams.
In addition, the following provisions will be satisfied:
surfaces of the geomembrane which are to be repaired will be abraded
no more than 30 minutes prior to the repair;
all surfaces must be clean, free of all particulate matter, and dry
at the time of the repair;
all seaming equipment used in repairing procedures must be approved;
the repair procedures, materials, and techniques will be approved in
advance of the specific repair by the Project Manager and CQA Consultant;
patches and caps will extend at least 150 mm beyond the edge of the
defect, and all corners of patches will be rounded with a radius exceeding
75 mm;
A novel method of patching the hole from
which a destructive sample is removed, is to place the patch on
the underside of the
geomembrane, by slipping a rectangular patch under the liner and
rotating 90° to fill the hole. There is no need to cut back the
flap of the original seam, the extrusion bead automatically seals
the end of the original seam air channel, and there is no need to
run-out the repair extrudate along the original seam and to possibly
overheat the geomembrane adjacent to the original seam.
the geomembrane below large caps should be appropriately cut to avoid
fluid entrapment between the two sheets and resultant pressure increases
(that stress the seams) as the liner is covered;
sharp ends of slits and cuts in the geomembrane should be rounded before
patches are placed over them; and
no more than one extrusion bead at any location will be used to make
a repair - multiple beading (more than two beads at any one location) is
not permitted and must be replaced with a patch.
Reseaming seams and multiple beading can overheat and may significantly
reduce the stress rupture resistance of adjacent geomembrane.
10.4.4 Verification of Repairs Each repair will be numbered and logged.
Each repair will be nondestructively tested using one of the methods described
in Section 10.3.8 or another approved method. Repairs which pass the nondestructive
test will be considered acceptable. Large caps may be of sufficient extent to
require destructive testing, at the discretion of the CQA Consultant. Failed
tests will require the repair to be redone and retested until a passing test
results. The CQA Consultant should observe all nondestructive testing of repairs
and will record the date of the repair and test result.
10.4.5 Large Wrinkles When
seaming of the geomembrane is completed (or when seaming of a large area
of the geomembrane is completed) and prior to placing overlying materials,
the CQA Consultant
will observe the sizes and distribution of geomembrane wrinkles. The CQA
Consultant will discuss with the Project Manager which wrinkles should be
cut and reseamed
by the Installer. The seam thus produced will be tested like any other
seam.
The amount and distribution of compensation to be built into
the lining system should be defined within the Project Specifications.
10.4.6 Bridging of Geomembrane Bridging or trampolining of the geomembrane
at any temperature higher than the design minimum service temperature or higher
than the expected covering temperature at any location at any time shall be considered
unacceptable. Compensating material will be installed at these locations. The
geomembrane must be fully supported by the subgrade at the time of covering with
soil or liquid. The minimum service temperature includes any period (after acceptance
of the installation by the owner) when the liner is uncovered even though final
service may involve covering the liner.
10.4.7 Geomembrane Anchoring The
CQA Consultant will ensure that the periphery of the geomembrane is anchored
in an anchor trench, welded to an HDPE strip cast into concrete, fastened
by a batten strip, or otherwise clamped, according to the design, such that
access
of liquid (contained liquids, rainwater) to the underside of the geomembrane
is prevented. The CQA Consultant will ensure that all gasketting and other
components of a
mechanical battening system are present according to the design. The CQA
Consultant will ensure that all butt and corner joints in cast in strips
have been welded
to provide water tight seals. The geomembrane will not be placed on loose
soil in the anchor trench. The geomembrane must be permanently anchored in
the anchor
trench, as soon as possible after installation, particularly in windy and/or
wet environments. However, it is advisable to allow the geomembrane to go
through one cold cycle (overnight) to evaluate the potential for contraction
and trampolining
before backfilling the trench. The geomembrane must lie flat against the
anchor trench front wall and floor. It must not be folded.
10.5 Backfilling of Anchor Trench Anchor trenches will be adequately
drained to prevent ponding or softening of the soils while the trench is
open. Anchor
trenches will be backfilled and compacted by the Earthwork Contractor or
the Installer as outlined in the specifications or drawings. Care will be
taken when
backfilling the trenches to prevent any damage to the geosynthetics. Sharp
rocks and stones shall be removed from soils before filling in the anchor
trench. There
shall be no holes in the geomembrane placed in the anchor trench. The CQA
Consultant will observe the backfilling operation and advise the Project
Manager of any
problems.
Erosion of side slopes has occurred when ponded
rainwater has leaked through a seam specimen hole in an uncovered
geomembrane in an anchor trench.
10.6 Appurtenances A copy of the specifications prepared by the Engineer
for appurtenances will be given by the Project Manager to the CQA Consultant
for review. The CQA Consultant will verify that:
installation of the HDPE geomembrane in appurtenance areas and connections
of geomembrane to appurtenances have been made according to specifications;
seaming of any gas vent or monitoring well boot to a cover geomembrane
is only done after cover soil has been placed to within about 3 m of each
vent or well, and initial settlement and movement of the cover has occurred.
extreme care is taken while seaming around appurtenances, since neither
nondestructive nor destructive testing may be feasible in these areas;
and
the geomembrane is supported as well as can be expected
at appurtenances.
The CQA Consultant will inform the Project Manager if the above conditions are
not fulfilled.