Title: Lining
Transformer Secondary Containment Structures:
EIA Geomembrane Construction Quality Assurance Plan
Written By: Ian
Peggs (I-CORP, INTERNATIONAL)
Date Written: 10/24/02
printable
version
1.0
INTRODUCTION
2.0 QUALITY PROGRAMS
3.0
PARTIES TO THE PROJECT
4.0 QUALIFICATIONS OF THE PARTIES
5.0
SCOPE OF CQA
6.0
UNITS
7.0 SUBMITTALS
8.0
PROJECT MEETINGS
9.0 GEOMEMBRANE MANUFACTURING
10.0
PANEL FABRICATION
11.0
PACKING AND TRANSPORTATION
12.0
GEOMEMBRANE STORAGE AND HANDLING ON SITE
13.0 INSTALLATION
14.0
RESPONSIBILITY FOR LINER
15.0
COVERING LAYERS
16.0
CQA REPORT
17.0 WARRANTY
1.0 INTRODUCTION
This
construction quality assurance (CQA) plan provides guidance to COMPANY
NAME’s environmental quality control (QC) and quality assurance (QA)
personnel (or their representatives) and their contractors involved
with the installation of geomembrane lining systems in existing concrete
secondary containment structures, such as under transformers. This
document specifically covers the use of PVC – KEE (ketone ethylene
ester) alloy geomembranes of which XR-5 is one trade-named product.
The
premise of geomembrane lining systems is that the geomembrane functions
solely as a barrier and not a load-bearing member of the system.
2.0 QUALITY
PROGRAMS
QC
is a system of procedures observed by a contractor on its own work
to ensure that the quality objectives are met.
QA
is a system of procedures observed by the owner or a third party to
ensure that the work of a contractor meets the designed objectives
with good workmanship. QA cannot be performed by a contractor on its
own work on behalf of the owner.
3.0 PARTIES
TO THE PROJECT
3.1 Resin
Manufacturer - manufactures the resin from which the geomembrane
rolls are made.
3.2 Geomembrane
Manufacturer – manufactures the geomembrane rolls. The geomembrane
manufacturer is ________________________.
3.3 Fabricator – assembles
the rolls into large panels in a controlled plant environment. The
fabricator is ___________________.
3.4 Installer – installs
the lining system. The installer is _________________________.
3.5 Project
Engineer – designs and is responsible for the functioning of
the lining system. The project engineer is __________________________.
3.6 CQA
monitor – the owner’s representative monitoring the quality of
the material and its proper installation. The CQA firm is _______________________.
3.7 CQA
laboratory – an independent laboratory that tests material samples
on behalf of the owner. The CQA laboratory is _______________________.
4.0 QUALIFICATIONS
OF THE PARTIES
4.1 Manufacturer
The
geomembrane manufacturer shall have manufactured at least 1,000,000
m2 of the same geomembrane proposed for use in the project
and shall have a comprehensive QA/QC program that provides a QC certificate
for each roll of geomembrane manufactured
4.2 Fabricator
The
geomembrane fabricator shall have fabricated at least 1,000,000 m2 of
the same geomembrane proposed for use in the project and shall have
a comprehensive QA/QC program that provides a QC certificate for each
panel of geomembrane fabricated and shipped to the site.
4.3 Installer
The
geomembrane installer shall have installed at least 500,000 m2 of
the same geomembrane as proposed for use in the project and shall have
a comprehensive QA/QC program that generates a formal comprehensive
QC report for the project engineer/owner.
The
installer shall have QC personnel specifically identified for monitoring
each project. This QC manager shall have experience of installing
at least 250,000 m2 of the same geomembrane proposed for
use in the project. The QC manager for the project is _______________________.
The
installer’s Master Seamer on the project shall have experience of welding
at least 250,000 m2 of the same geomembrane as proposed
for use in the project, of which at least 50,000 m2 shall
be in concrete structures. The Master Seamer is ______________________.
4.4 CQA
CQA
personnel shall have performed CQA on at least 500,000 m2 of
reinforced geomembrane of which at least 50,000 m2 is the
same geomembrane as proposed for use in the project. The CQA Superintendent
is __________________.
4.5 CQA
Laboratory
The
laboratory shall be accredited with the Geosynthetic Accreditation
Institute Laboratory Accreditation Program (GAI-LAP) for all tests
to be performed on the project geomembrane and its seams.
5.0 SCOPE
OF CQA
The
scope of this CQA Plan includes:
1. Review
of project documents
2. Resin
manufacturing
3. Geomembrane
manufacturing
4. Geomembrane
panel fabrication
5. Transportation
and handling
6. Condition
of concrete and soil substrates
7. Liner
installation
8. Material,
seam, and liner testing
9. Covering
the geomembrane
6.0 UNITS
In
this CQA Plan, all parameters, properties, and dimensions are expressed
in SI units. If the geomembrane manufacturer, fabricator, or installer
provide US or Imperial units a hard conversion to SI units shall govern. Conversion
factors shall be as presented in ASTM standard E380.
The
CQA laboratory shall provide all test results in SI units.
7.0 SUBMITTALS
The
following submittals shall be required with the Installer’s proposal:
- Resin
manufacturer’s QC Program including a sample of a QC certificate
- Geomembrane
manufacturer’s QC Program including a sample of a roll QC certificate
- Manufacturer’s
geomembrane specification sheet
- Manufacturer’s
list of recent projects totaling 1,000,000 m2 and associated
contact details
- Fabricator’s
QC Program including a sample of a panel QC certificate, and a sample
of a factory seam
- Fabricator’s
list of recent projects totaling 1,000,000 m2 and associated
contact details
- Details
of folding/rolling panels for shipping
- Installer’s
QC Program including samples of all field logs/records, a sample
of a field seam, and an outline of a final installation report
- Installer’s
list of recent projects totaling 500,000 m2 and associated
contact details
- Details
of all liner connections at batten strips, pipe penetrations, grounding
wire penetrations, and inside corners
- A
list of questions concerning any unclear items in project documentation
The
following submittals will be required two weeks prior to delivery of
material to the site:
1. Installer’s
proposed panel layout for the project
2. Resume
of proposed QC manager for the project and a list of recent projects/contacts
3. Resume
of proposed Master Seamer for the project and a list of recent projects/contacts
4. A
statement by the Installer that all project documents have been reviewed,
all queries satisfactorily answered, and that all project requirements
can be complied with by manufacturer, fabricator, and installer
The
following submittals will be required prior to shipping materials from
the Fabricator:
1. Resin
QC certificate
2. Manufacturer’s
QC certificates for each roll of geomembrane
3. Fabricator’s
QC certificates for each panel, including test results for each factory
seam. Seam tests shall be performed on production seams and not on
separately made seam samples.
No
material shall be shipped from the Fabricator prior to receipt of these
documents nor without the approval of the Project Engineer.
8.0 PROJECT
MEETINGS
Prior
to the start of liner installation a Preconstruction meeting shall
be held between Owner, Project Engineer, Installer, and CQA superintendent
to jointly agree on the installation procedures and to clarify any
unclear details of project documents.
An
Action Decision Meeting will be held when a problem occurs that requires
a procedural decision by the Owner/Project Engineer. The problem
shall be documented together with proposed actions, the action finally
agreed upon, and the party responsible for implementation of the action.
9.0 GEOMEMBRANE
MANUFACTURING
The
geomembrane material shall be an ethylene interpolymer alloy (EIA)
such as 8130 XR-5 manufactured by Seaman Corporation, or an equivalent
EIA with specifications as shown in Table 1.
All
rolls shall be manufactured from the same batch of resin.
Rolls
shall have the reinforcement covered by polymer along each edge.
Table
1. Geomembrane specifications
|
Parameter
|
Test
Method
|
Value
|
|
Thickness
|
ASTM
D5199
|
>0.75
mm
|
|
Break
Strength
|
ASTM
D4632
|
>2.45
kN
|
|
Puncture Strength
|
ASTM
D4833
|
>1.10
kN
|
|
Tear
Strength
|
ASTM
D4533
|
>150
N
|
|
Low
temperature
resistance
|
ASTM
D2136
(4
hr, 3 mm)
|
<-350C
|
|
Ply
adhesion
|
ASTM
D413
|
>2.5
N/mm
|
|
Dimensional
stability
|
ASTM
D1204
(1000C,
1 hr)
|
<1.0%
|
10.0 PANEL
FABRICATION
Geomembrane
rolls shall be fabricated into large panels under controlled environmental
conditions. Welds shall be made using hot wedge or dielectric equipment. Welds
shall be single track welds a minimum of 25 mm wide or double track
welds.
The
welding process shall generate similar small visible “squeeze-out” beads
along each edge of each seam. The reinforcement shall not be exposed
along roll edges.
All
seams shall be 100% nondestructively tested using the air lance technique.
One
seam at each end of each panel (not the same seam) shall be destructively
tested in peel and shear according to ASTM standard D751 as modified
in National Sanitation Foundation International Standard NSF 54. Five
specimens shall be tested in peel and five in shear from both samples. Both
samples shall meet the seam specifications listed in Table 2.
Table
2. Seam specifications
|
Parameter
|
Test
Method
|
Value
|
|
Shear
strength
|
ASTM
D751
(mod
NSF 54)
|
>2.45
kN
|
|
Peel
strength
|
ASTM
D751
(mod
NSF 54)
|
>30
N/mm
|
11.0 PACKING
AND TRANSPORTATION
When
possible panels shall only be rolled for shipping. If panel widths
require it, they shall be accordion folded along the length and rolled
for shipping to the site. A rigid core shall be used to aid with
handling. Panels will not be accordion folded in more than one direction.
Each
panel shall be identified with a label showing product type, panel
number, width, length, and weight.
Sufficient
excess material shall be supplied to allow discarding of the outer
wrap should it be damaged during shipment and on-site storage and handling.
The
bed of the shipping truck shall be examined carefully and all sharp
rough objects removed prior to loading the geomembrane rolls.
12.0 GEOMEMBRANE
STORAGE AND HANDLING ON SITE
Geomembrane
rolls shall be lifted from the truck using appropriate equipment with
at least two broad slings.
Rolls
shall be stored on a smooth flat clean surface in a location close
to the transformer where they will not be damaged, where there is no
possibility of standing water, and where they will not become dirty.
Rolls
shall be stacked no more than three high.
13.0 INSTALLATION
Folded
geomembrane panels shall not be unrolled or unfolded at geomembrane
temperatures below 0oC. Panels may, however, be unrolled
at lower temperatures if they have not been folded.
13.1 Subgrade
The
surface of the concrete on which the geomembrane is to be placed shall
be carefully examined for unacceptable roughness and steps exceeding
2 mm in height or depth. Any such roughness shall be ground smooth
or filled. Cracks exceeding 1 mm in width shall be filled with a
supporting grout. Outside corners shall be rounded to a minimum radius
of 5 mm.
Any
soil subgrade shall be compacted smooth to an adequate uniform density
to prevent differential settlement. The top 50 mm of the subgrade
shall be free from angular rocks larger than 5 mm, roots, grass, and
biodegradable vegetation. Foreign materials and protrusions exceeding
5 mm shall be removed. All desiccation cracks shall be filled/smoothed
and all steps exceeding 5 mm shall be smoothed.
The
subgrade surface shall be maintained in a firm, clean, smooth, and
dry condition during liner installation. Unless otherwise agreed
the Installer shall be responsible for maintaining the condition of
the subgrade surfaces.
The
Installer shall provide and sign documentation indicating that the
subgrade is acceptable for the installation of the geomembrane and
that it will not compromise the performance of the geomembrane.
The
geomembrane shall be installed without stress and in such a way that
it is fully supported by the subgrade, including in 90o inside
corners. It shall not bridge corners or other geometrical features.
The
number of field seams shall be minimized.
13.2 Batten
strip attachments
Batten
strip attachments to the concrete shall be made according to the project
drawings or according to ASTM standard D6497. Batten strips shall
be manufactured using Type 304 stainless steel with a minimum cross
section of 35 mm by 7 mm. Type 304 stainless steel threaded stock
and bolts shall be used at a maximum center-to-center spacing of 300
mm. The nearest fastener shall be centered no more than 75 mm from
the end of a batten strip. Batten strips shall extend completely
into the inside, or to the edges of outside, corners. At inside
corners and at other locations where the geomembrane could be tensioned
against a corner of the batten strip the corner shall be ground round
and smooth. Similarly, at outside corners where sharp corners on
the batten strip might present a hazard to workers the corners of the
batten strip shall be ground round and smooth.
The
primary gasket, between geomembrane and concrete shall be a non-connected
porosity neoprene rubber. There shall also be secondary gasketing
between the batten strip and the geomembrane, in which the bolt holes
shall be no larger than the bolts. Elongated holes in the batten
strip shall be filled with sealant compressed by the washer under the
fastening nut.
At
inside and outside corners where tightening the batten strips might
lift the geomembrane away from the corner, sealant shall be carefully
placed between the geomembrane and the concrete.
Pipe
penetrations shall be booted according to the project drawings or according
to ASTM standard D6497. Corrugated pipes shall be replaced with smooth
plastic pipes.
Every
attempt shall be made to avoid folds and creases in the geomembrane
particularly under batten strips. Folds (commonly referred to as “fishmouths”)
shall be cut along the peak, the edges overlapped and a hot-air seam
made to minimize the thickness of the liner behind the batten strip. Where
folds are unavoidable, a thin layer of sealant shall be placed on the
mating surfaces inside the fold, to eliminate leakage down the inside
of the fold.
At
features such as fishmouths and folds that are cut, overlapped, and
seamed, where there is insufficient overlap to make an effective seam,
such as at the end of the cut, a patch shall be placed over the end
of the cut.
When
liner edges are left exposed for any length of time, such as overnight,
they shall be suitably ballasted (using sandbags, undamaged tires,
or other smooth-surface items) against uplift by reasonably expected
winds.
13.3 Trial
Seaming
Prior
to the start of a production seaming shift and at least every 5 hr
a trial seam shall be made by each weld machine/operator combination
using a fragment of geomembrane. The trial seam shall be made under
the conditions of the planned production seaming – on a horizontal
or vertical concrete or soil substrate accordingly. The trial seam
shall be at least 1.5 m long.
Five
peel and five shear specimens shall be cut from the center of the trial
seam and tested alternately in peel, shear, peel, shear, etc. All
specimens shall meet the seam specifications listed in Table 2. In
the event of nonconformance, an additional trial seam shall be made
and tested. If this still fails to meet specifications the welding
machine shall be examined and adjusted and not used for production
seaming until two passing trial welds have been made.
New
trial welds will be required whenever the geomembrane temperature changes
by more than 25oC.
13.4 Production
Seaming
Production
seaming shall only commence when passing trial seams have been made. If
adjustments to the machine are felt to be necessary, the machine is
switched off for any reason, or the operator is changed, new passing
trial welds will be required before production seaming can continue.
At
least once per hour a field seam shall be extended longer than required
and four specimens removed from it – two to be tested in peel and two
in shear. All four specimens shall meet seam specifications. If
seam specifications are not met the seam shall be sampled at intermediate
locations since the last passing test until the full extent of the
nonconformance can be defined. The seam shall be made good from the
last passing test sample.
When
recording seam test data all failing test data shall be recorded.
13.5 Nondestructive
testing
Every
millimeter of all seams shall be nondestructively tested by air lance
testing (single track welds), air pressure testing (dual track welds)
according to ASTM standard D5820, or vacuum box testing (single track
welds) according to ASTM standard D5641.
13.6 Seam
edge air lance testing
Air
lance testing will performed using a 5 mm diameter nozzle and an air
pressure exceeding 400 kPa with the nozzle held no more than 100 mm
from the edge of the seam. The speed of the nozzle along the edge
of the seam shall not exceed 15 m/min. Any location of seam edge
flapping, whistling, or other abnormal motion/noise shall be marked
for repair.
13.7 Center
channel air pressure testing
When
air pressure testing is performed the applied pressure shall be between
165 and 210 kPa, and pressure loss shall not exceed 4 kPa in 5 minutes
after a 2 minute stabilization period. At the conclusion of the test
the pressure shall be released from the opposite end of the seam to
the end at which the pressure is applied to demonstrate that the full
length of seam has been tested. All needle holes shall be repaired.
13.8 Vacuum
box testing
When
vacuum box testing is performed, the applied vacuum shall be between
20 and 35 kPa. The locations of any bubbling within 10 seconds of
vacuum application shall be repaired.
At
the conclusion of seam nondestructive testing the complete lining system
shall be filled with water to at least 50 mm above the top edge of
the highest batten strip for a hydrostatic pressure test. With all
outlets sealed, the water level decrease shall not exceed 20 mm in
24 hr. If this loss rate is exceeded the source of leakage shall
be located, repaired, and the structure refilled and retested.
Where
possible inner and outer sections of the containment structure shall
be hydrostatically tested separately.
13.9 Laboratory
testing
Samples
shall be removed by the project engineer from the ends of two factory
seams of each panel delivered to site for CQA laboratory testing. Testing
shall be performed according to ASTM D751 (modified by NSF 54) and
the specifications of Table 2 shall be met by all five peel and all
five shear specimens. Failure of this testing shall result in rejection
of the panel which shall be replaced by the Installer at its expense.
A
section of at least one trial seam made by each machine/operator combination
each day shall be submitted to the CQA laboratory for seam testing
according to ASTM D751 (modified by NSF 54). All five peel and shear
specimens shall meet project specifications as listed in Table 2. A
failure of this testing shall result in removal of a sample from the
field seam previously made by that machine, for CQA laboratory testing. Failure
of this additional sample shall result in rejection of all field seams
made by that machine/operator combination since the last sample passed
by the CQA laboratory.
13.10 Defects
and repairs
All
repairs will be made using a patch cut from the geomembrane material
delivered to site.
Patches
will overlap any damaged area by at least 75 mm in all directions.
Patches
will have rounded corners and will be attached using hot air welding
equipment such that there are no loose edges.
All
patches will be tested using an air lance or a vacuum box.
Patches
shall not be placed overlapping other patches. Where this might occur
one large patch will be placed to avoid the appearance of multiple
patches.
14.0 RESPONSIBILITY
FOR LINER
The
liner will remain the responsibility of the Installer until a completed
construction report has been presented to the Owner by the Installer
and all test results have been satisfactorily obtained from the CQA
laboratory. The construction report will include:
- Material
QC certificates
- Subgrade
acceptance documents
- Trial
welding records, including all failing test details
- Production
welding records
- All
seam test results including failing results
- All
repair records, including test results
- All
hydrostatic test data
- Details
of any problems and their resolution e.g. concrete condition, pipe or
grounding wire penetrations
- Modifications
to liner required during construction
- Copies
of Manufacturer’s and Installer’s warranties
- Evidence
of satisfactory covering of the geomembrane when covering layers
are the responsibility of the installer
15.0 COVERING
LAYERS
The
geomembrane shall be covered in such a way that it is not damaged.
A
nonwoven polypropylene (stabilized against ultraviolet and thermal
degradation) geotextile cushion layer, with a minimum mass/unit area
of 540 g/m2 shall be used. Geotextile overlaps shall be
stitched or thermally bonded.
A “fire
quenching” layer of 19 – 37.5 mm crushed stone shall be placed on top
of the geotextile without damaging the geomembrane. The crushed rock
shall not be dumped directly from a truck onto the liner. It shall
initially be dumped on to adjacent ground and spread from there by
wheelbarrow, or other moving equipment, to produce an area with a thickness
of at least 600 mm. Care shall be taken that projections on the equipment
do not damage the liner when it is emptied. Subsequently, stones
may be dumped on this area, and spread from there using motorized equipment
with ground pressures of less than 75 kPa. Nevertheless such equipment
shall not stop or start suddenly, nor turn sharply such that shear
forces are generated at the stone/geotextile/geomembrane interfaces.
The
covering layer shall be a minimum of 750 mm thick.
16.0 CQA
REPORT
A
CQA report will be prepared by the Project Engineer to demonstrate
clearly that all requirements of the project specifications, the project
drawings, and this CQA Plan have been complied with. The objective
of the CQA Plan is to provide full traceability of materials, men,
and equipment such that the potential extent of any problem that arises
during service can be quickly defined.
17.0 WARRANTY
TO
BE COMPLETED BY COMPANY NAME IF REQUIRED. WARRANTY SHOULD BE AT LEAST
ONE YEAR ON INSTALLATION (FIVE YEARS SHOULD NOT BE UNREASONABLE, AS
PROVEN BY AN ANNUAL HYDROTEST) AND 20 YEARS ON MATERIALS. HOWEVER,
A 20 YEAR PRO-RATED MATERIALS WARRANTY HAS RELATIVELY LITTLE PRACTICAL
VALUE. THE FABRICATOR SHOULD ALSO PROVIDE A WARRANTY OF AT LEAST
TEN YEARS ON THE FACTORY SEAMS.
|