addresses, phone numbers and email for geosynthetica.net
Who we are and what we do! addresses, phone numbers and email for geosynthetica.net
Comprehensive Library of Abstracted Publications - Books, Proceedings, Periodicals etc. International Standards Listings & Cross Reference Workshops, Conferences, Symposia &  Other Events Employees &  Employers in the Geosynthetics Industry Tools for Converting Metric & Imperial Units of Measure
Guidance Documents, Case Studies, CQA Plans, Forms, Articles etc.  2000+ Geosynthetics Individual Listings Industry Organizations, Publications & Useful Web Sites Check on This Week's Resin Pricing Tools & Resources for Virus Protection & Removal
click for a listing of our underwriters and their products & services

 

Title: Installation Specification HDPE
By: Ian Peggs, I-CORP INTERNATIONAL


 

10.1 Earthwork

10.1.1 Surface Preparation
10.1.2 Anchorage System

10.2 Geomembrane Placement

10.2.1 Field Panel Identification
10.2.2 Field Panel Placement

10.2.2.1 Location
10.2.2.2 Compensation for Material Expansion and Contraction, OR
10.2.2.2 Intimate Subgrade Contact
10.2.2.3 Installation Schedule
10.2.2.4 Weather Conditions
10.2.2.5 Method of Placement
10.2.2.6 Damage

10.3 Field Seaming

10.3.1 Seam Layout
10.3.2 Seaming Equipment and Products

10.3.2.1 Fusion Seaming
10.3.2.2 Extrusion Seaming

10.3.3 Seam Preparation
10.3.4 Weather Conditions for Seaming
10.3.5 Overlapping and Temporary Bonding
10.3.6 Trial Seams
10.3.7 General Seaming Procedure
10.3.8 Nondestructive Seam Continuity Testing

10.3.8.1 Concept
10.3.8.2 Submittals
10.3.8.3 Vacuum Testing
10.3.8.4 Air Pressure Testing
10.3.8.5 Spark Testing
10.3.8.6 Visual Examination

10.3.9 Destructive Testing

10.3.9.1 Concept
10.3.9.2 Location and Frequency
10.3.9.3 Sampling Procedure
10.3.9.4 Size of Samples
10.3.9.5 Field Testing
10.3.9.6 Construction Quality Assurance Laboratory Testing
10.3.9.7 Installer's Laboratory Testing
10.3.9.8 Destructive Sample Pass/Fail Criteria
10.3.9.9 Procedures if Destructive Sample Fails

10.4 Defects and Repairs

10.4.1 Identification
10.4.2 Evaluation
10.4.3 Repair Procedures
10.4.4 Verification of Repairs
10.4.5 Large Wrinkles
10.4.6 Bridging of Geomembrane
10.4.7 Geomembrane Anchoring

10.5 Backfilling of Anchor Trench

10.6 Appurtenances


10. GEOMEMBRANE INSTALLATION

10.1 Earthwork

10.1.1 Surface Preparation

The Earthwork Contractor will be responsible for preparing the supporting soil according to the project specifications. The CQA Consultant will verify that:

  • a qualified Land Surveyor has established all lines and grades, and they are approved by the Project Manager;
  • the supporting soil meets the density specification;
  • the surface to be lined has been finished so as to be free of irregularities, protrusions, loose soil, dessication cracks and abrupt changes in grade;
  • the 50 mm surface layer of the  supporting soil  does not contain stones or other objects which may be damaging to the geomembrane; and
  • there are no areas excessively softened by high water content.

The Installer will certify in writing that the surface on which the geomembrane will be installed within the next 24 hr is acceptable.  The certificate of acceptance will be given by the Installer to the Project Manager prior to commencement of geomembrane installation in the area under consideration.  The CQA Consultant will be given a copy of this certificate by the Project Manager.  The CQA Consultant will also acknowledge approval of the subgrade.

After the supporting soil has been accepted by the Installer, it will be the Installer's responsibility to indicate to the Project Manager any change in the supporting soil condition that may require repair work.  If the CQA Consultant concurs with the Installer, then the Project Manager will ensure that the supporting soil is repaired.

10.1.2 Anchorage Trenches

Anchor trenches will be excavated by the Earthwork Contractor (unless otherwise specified) to the lines and dimensions shown on the design drawings, prior to geomembrane placement.  The CQA Consultant will verify that anchor trenches have been constructed according to the design drawings.

The edge of the trench, over which the geomembrane enters the trench, will be rounded to avoid sharp bends in the geomembrane. There shall be no sharp protrusions on the inside wall of the trench. No loose soil will be allowed to underlie the geomembrane in the trenches.

Water shall not be allowed to stand, or soften the soil, in the anchor trench.  Responsibility for dewatering of the anchor trench shall be as agreed upon in the contract or at the Preconstruction Meeting.

Backfilling of anchor trenches will be conducted in accordance with Section 10.5.

10.2 Geomembrane Placement

Before any geomembrane is deployed the documents listed in Appendix B must be received from the Installer and be reviewed and approved by the CQA Consultant and Project Manager.

10.2.1 Field Panel Identification

A field panel is a single piece of geomembrane (other than a patch or cap strip) which is seamed in the field: i.e. a roll or a portion of roll cut in the field.

It will be the responsibility of the CQA Site Superintendent to ensure that each field panel is given an "identification code" (number or letter-number) consistent with the layout plan.  This identification code will be agreed upon by the Project Manager, Installer, and CQA Consultant.  This field panel identification code should be as simple and logical as possible.  It will be the responsibility of the Installer to ensure that each field panel placed is also marked with the original roll number.  The identification code and roll number will be marked at a location agreed upon by the Project Manager, Installer, and CQA Consultant.

Typically, panels will be numbered in the order in which they are placed. The CQA Site Superintendent will establish a table or chart showing correspondence between roll numbers and field panel identification codes.  The field panel identification code will be used for all CQA records.

10.2.2 Field Panel Placement

No geosynthetics shall be deployed, joined, or tested unless a representative of the CQA Consultant is present to monitor such activities. 

10.2.2.1 Location

The CQA Consultant will verify that field panels and seam orientations are approximately as indicated in the Engineer's or Installer's approved layout plan, or as modified.

It is not practical to expect the field panels to be laid in exact conformance with the panel layout plan, due to three dimensional subgrade profiles that cannot be projected on two dimensional drawings.  Thus, it is impossible for the installer to provide a pre-numbered layout schedule to which he will rigorously adhere.

10.2.2.2 Compensation for Material Expansion and Contraction

A minimum coefficient of linear thermal expansion of 1.5 x 10-4°C-1 should be used for HDPE geomembrane.  The actual value will depend on the temperature range of interest.  Actual geomembrane, not ambient, temperatures must be used to calculate the amount of compensation required for expansion and contraction.  Alternatively, procedures could be defined that require the geomembrane to be immediately covered while in 100% intimate contact with the subgrade.

Unless provided by the designer, as it should be, the Installer will be responsible for determining the required amount of compensation that must be installed in the geomembrane to ensure that it will not be unduly tensioned due to temperature variations in service.  Such calculations shall be shown to the CQA Consultant and Project Manager.  The Installer will be responsible for ensuring that sufficient HDPE geomembrane is installed to compensate for contraction of the material during anticipated lower temperatures and to prevent expansion and excessive wrinkling at possible higher covering temperatures.

The latter is clearly very difficult to achieve.  Compensation wrinkles should be small and frequent rather than large and infrequent.  Their performance is a function of flexural modulus and interface shear strength with the subgrade.

The methods of installing compensation will be discussed with, and approved by, the Project Manager and the CQA Consultant. The geomembrane must not be tensioned and must be fully supported by the subgrade when it is covered by soil or liquid ballast.

In some countries (e.g. Germany) the geomembrane must be placed without wrinkles.  Installation practices have been developed to do this.    This requires placing complete sections of the lining system adjacent to one another.  However, such practices can not necessarily be taken and applied to other countries (e.g. USA) since common US practice is to lay the lining system in complete individual layers.    The procedures for laying the geomembrane should be outlined in the Project Specifications. The procedure for wrinkle-free installation is as follows:

· Install a suitable section of geomembrane within one day that has minimal wrinkling;

· Cover the geomembrane with cushion geotextile or required geosynthetic layers;

· At the end of the day place cover soil/stone around the periphery of the deployed area to act as ballast, and to prevent the geomembrane from contracting during lower overnight temperatures;

· When the liner is still somewhat tensioned and flat during the low morning temperatures, spread the soil/stone across the flat geomembrane; and

· Proceed to lay an adjacent section of geomembrane without wrinkles.

It should be noted that this method of deployment is slower than a typical North American site, so if specified it will likely incur a cost premium.

If this, or a similar procedure is required in the Project Specifications, Section 10.2.2.2 of the CQA Plan should read as follows:

10.2.2.2 Intimate Subgrade Contact

Note that this section will, if used, replace the previous section 10.2.2.2.

Only that amount of geomembrane will be deployed in one day that can be covered by other required geosynthetics and the required thickness of cover soil.  The cover soil will initially be placed as ballast around the periphery of that section of geomembrane.

The CQA Consultant will monitor the placement of geomembrane and soil to confirm that the geomembrane is essentially in complete contact with the subgrade at the end of the working day, and is restrained in this position, without excessive tension, by the peripheral soil.

The CQA Consultant will monitor the spreading of cover soil at the start of the first shift of the next day to confirm that no standing or folded wrinkles in the geomembrane are covered by soil.

The geomembrane must be in intimate contact with the subgrade. At all times the exposed edges of geosynthetics will be kept clean and protected from damage.

10.2.2.3 Installation Schedule

Field panels will be placed one at a time, and each field panel will be seamed immediately after its placement (in order to minimize the number of unseamed field panels exposed to wind). It is beneficial to "shingle" overlaps in the downslope direction to facilitate drainage in the event of precipitation, shingling should also be done in the downstream direction to minimize resistance to flow.

It is also beneficial to proceed downslope and in the direction of (with) prevailing winds.  Scheduling decisions must be made during installation, in accordance with varying environmental conditions.  In any event, the Installer will be fully responsible for the decisions made regarding placement procedures.

The CQA Consultant will evaluate every change in the schedule proposed by the Installer and advise the Project Manager on the acceptability of that change. The CQA Consultant will verify that the condition of the supporting soil is still satisfactory for installation of geomembrane.

The CQA Consultant will record the identification code, roll number, location, weather conditions, and date of installation of each field panel.

10.2.2.4 Weather Conditions

Geomembrane placement will not proceed at geomembrane temperatures below -20°C unless approved by the project engineer.  Geomembrane seaming will not proceed at geomembrane temperatures between 0°C and -20°C or above 75°C unless approved by the Project Manager.  Approval will not be unreasonably withheld provided the Installer can demonstrate the ability to produce satisfactory seams. The frequency of trial seams, or seam destructive test sampling, (Section 10.3.6) may be increased at extreme geomembrane temperatures (<5°C, >75°C).  Geomembrane placement will not be done during any precipitation, in an area of ponded water, or during excessive winds except as approved in an Action Decision Meeting.

NOTE: The only temperature of significance is the actual geomembrane temperature, not the ambient temperature.  When exposed to sunlight the geomembrane temperature will be significantly higher than ambient.

  At low geomembrane temperatures destructive specimens can be removed from the beginning and end of each seam.  

The CQA Consultant will verify that the above conditions are observed.  Additionally, the CQA Consultant will verify that the supporting soil has not been damaged by weather conditions.   The CQA Site Superintendent will inform the Project Manager if the above requirements are not observed.

10.2.2.5 Geomembrane Placement

The CQA Consultant will verify that:

  • equipment used does not damage the geomembrane as a result of handling, trafficking, excessive heat, leakage of hydrocarbons, or by other means;
  • any All-Terrain Vehicles (ATVs) used to deploy geosynthetics exert ground pressures less than 55 kPa (8 psi);
  • ATVs are not operated:  1) at excessive speeds, 2) in tight turning circles, 3) under extreme breaking and accelerating conditions, 4) with dirty tires, and 5) over wrinkles, that might damage the geomembrane;
  • the prepared surface underlying the geomembrane has not deteriorated since previous acceptance, and is still acceptable immediately prior to geomembrane placement;
  • any geosynthetic elements immediately underlying the geomembrane are clean and free of debris;
  • personnel working on the geomembrane do not smoke, do not wear hard-soled shoes, and do not engage in activities which could damage the geomembrane;
  • frequently used pathways up and down geomembrane on slopes are protected by a roll of geotextile;
  • the methods used to unroll the panels do not cause excessive scratches or crimps in the geomembrane and do not damage the supporting soil;
  • the method used to place the panels minimizes wrinkles (especially differential wrinkles between adjacent panels);
  • geomembrane is not allowed to unroll freely down a slope;
  • geomembrane is not placed under tension, unless approved by the Project Manager;
  • adequate temporary loading and/or anchoring (e.g., sand bags, tires), that does not damage the geomembrane, has been placed to prevent uplift by wind;
  • direct contact of equipment with the geomembrane shall not be allowed, except as previously described for ATVs used to deploy geosynthetics. The geomembrane shall be protected by geotextiles, extra geomembrane, soil layers, or suitable materials, in areas where equipment may be used or traffic may be expected;
  • only hook bladed utility knives are used to cut through the geomembrane;
  • appropriate care is to be taken to prevent shock and explosions caused by static electricity discharges;
  • all handholds cut for moving panels and damage caused by clamps are repaired; and
  • panels are not moved such that subgrade soil can peel the underside seam flap.  

The CQA Site Superintendent will inform the Project Manager if the above requirements are not observed.

10.2.2.6 Temporary Ballasting

Temporary ballasting around the edges of the installed liner shall be done with sandbags or equivalent non-damaging ballast material (e.g. tires without reinforcing wires exposed).  Sandbags shall be handleable by one person and shall be spaced to provide adequate uplift protection against typical winds that might reasonably be expected to occur prior to the addition of adjacent panels or prior to permanent ballasting.

10.2.2.7 Damage

The CQA Consultant will visually examine each panel, after placement and prior to seaming, for damage.  The CQA Site Superintendent will advise the Project Manager which panels, or portions of panels, should be rejected or repaired.  Damaged panels or portions of damaged panels, which have been rejected will be marked, and their removal from the work area recorded by the CQA Consultant.  Repairs will be made according to procedures described in Section 10.4.

At a minimum, the CQA Consultant will ensure that:

  • each panel is placed in such a manner that it has not been, or is unlikely to be, damaged; and
  • any tears, punctures, holes, thin spots, and damaging inclusions, gouges, and protuberances etc., are marked for repair, or the panel is rejected.

10.3 Field Seaming

10.3.1  Seam Layout

Prior to the commencement of installation activities the Installer will provide the Project Manager and the CQA Consultant with a proposed panel layout drawing.  The CQA Consultant will review the panel layout drawing and verify that it is consistent with the accepted state-of-practice and this CQA Plan.  No panels may be seamed in the field without the Project Manager's approval.  In addition, panels that significantly change the layout drawing, (e.g. that change the orientation of seams) shall not be installed without the Project Manager's prior approval.  It is, however, recognized that such a drawing is only a guide and will, in practice, require modification.

In general, seams should be oriented parallel to the line of maximum slope, i.e., oriented up and down, not across, the slope.  In corners and other geometrically complex locations, the number of seams should be minimized.  No base seam or tee seam will be less than 2 m from the toe of slopes, or areas of potential stress concentrations, unless otherwise authorized by the Project Manager.

If roll end seams are unavoidable on slopes, the upslope panel shall overlap the downslope panel and adjacent panel cross-seams shall be staggered by at least 2 m.

A seam numbering system compatible with the panel numbering system will be agreed upon at the Resolution or Preconstruction Meeting. 

  Seams are usually identified by the panel numbers on each side, e.g. seam 1 / 2, for the seam between panels 1 and 2.  

10.3.2 Seaming Equipment and Products

Approved methods for field seaming are thermal fusion (hot wedge, hot air, or combination) seaming and extrusion seaming.  Proposed alternate methods will be documented and submitted to the Project Manager and CQA Consultant for approval.  Only apparatus that has been specifically approved by make and model will be used.  The Installer will use appropriate measuring equipment to ensure that required temperatures are being achieved.

  A combination of hot wedge and hot air probably produces the most durable seam.  Ultrasonic and electrofusion seaming methods are also available, but are not yet well established.  

The Project Manager will submit all documentation to the CQA Consultant for his concurrence.

10.3.2.1  Fusion Seaming

Fusion seaming must be done with automated self-propelled machines.  The fusion seaming machines will be equipped with gauges giving hot wedge temperatures.  Temperature, speed, and nip roll pressure settings will be verified by the Installer prior to each seaming period. Nip roll and wedge geometries shall be such as to minimize residual stresses at the edge of the seam, i.e. to minimize reduction in stress cracking resistance of the geomembrane.

The CQA Consultant will log ambient conditions, geomembrane temperatures,  seaming apparatus temperatures and speeds, equipment serial number, and operator initials.

The CQA Consultant will also verify that:

  • the Installer maintains on-site the number of operable seaming machines decided at the Resolution Meeting;
  • equipment used for seaming does not damage the geomembrane;
  • for tee seam intersections, all edge flaps are cut back to the edge of the outer-most peel-tested track of the seam prior to seaming;
  • electric generators and fuel containers are placed on a smooth protective layer such that no damage occurs to the geomembrane;
  • a smooth insulating plate or fabric is placed beneath the hot seaming apparatus after usage;
  • the geomembrane is protected from damage in heavily-trafficked areas; and
  • build-up of moisture between the sheets is prevented. To accomplish this a movable protective layer may be used directly below each overlap of geomembrane that is to be seamed.

10.3.2.2 Extrusion Seaming

Extrusion-seaming apparatus will be equipped with gauges giving the relevant temperatures of the apparatus such as the temperatures of the extrudate, nozzle, and preheat air.

The Installer will provide documentation (including QC certificates) regarding the welding rod or resin pellets to the Project Manager and the CQA Consultant, that show that the resin is the same HDPE resin as the geomembrane itself.  Other seaming resins must be approved by the Project Manager and the CQA Consultant.

The CQA Consultant will log apparatus temperatures, extrudate temperatures, ambient conditions, and geomembrane temperatures at appropriate intervals.

The CQA Consultant will verify that:

  • the Installer maintains on-site the number of operable seaming machines decided at the Resolution Meeting;
  • equipment used for seaming will not damage the geomembrane;
  • the extruder is purged prior to seaming until all heat-degraded extrudate has been removed from the barrel;
  • feed resin is maintained clean and dry;
  • the electric generator and fuel containers are placed on a smooth intermediate layer such that no damage occurs to the geomembrane;
  • a smooth insulating plate or fabric is placed beneath the hot seaming apparatus after usage; and
  • the geomembrane is protected from damage in heavily trafficked areas.

10.3.3  Seam Preparation

The CQA Consultant will verify that:

  • prior to seaming, the seam area is clean and free of moisture, dust, dirt, debris of any kind, foreign material, and any mechanical damage;
  • if seam overlap grinding is required, the process is completed according  to the Manufacturer's instructions but within 30 minutes of the seaming operation, and in a way that does not damage the geomembrane;
  • the abrading does not remove more than 10 percent of the thickness of the geomembrane, and the resulting abrasion marks are covered by the finished extrusion bead;
  • any visible abrasion marks, after seaming, are essentially perpendicular to the direction of the seam;
  • the abrading does not introduce damaging gouges in the geomembrane; and
  • seams/panels are aligned with a minimum of wrinkles and "fishmouths".

10.3.4 Weather Conditions for Seaming

The following protocols will be observed during seaming:

  • Unless authorized in writing by the Project Manager, no seaming will be attempted at geomembrane temperatures below -0°C or above 75°C;
  • Below a geomembrane temperature of 5°C, the need for pre-heating and additional testing should be discussed with the Project Manager and CQA Consultant;
  • In all cases, the geomembrane in the seaming area will be dry and protected from wind and airborne particulates; and
  • Geomembrane temperatures will be measured with a surface temperature thermocouple or a calibrated infrared pyrometer.

If the Installer wishes to use methods which may allow seaming at geomembrane temperatures below 0°C or above 75°C, the Installer will demonstrate (by testing trial seams) that such methods produce seams which are entirely equivalent to seams produced at geomembrane temperatures above 0°C and below 75°C, and that the overall quality of the seam and durability of the geomembrane are not adversely affected.  In addition, the Installer will prepare written certification that states that the seaming procedure does not cause any physical or mechanical modification to the geomembrane that will generate any short or long-term damage to the geomembrane liner.

The CQA Consultant will verify that these requirements are observed and will advise the Project Manager if potential problems are perceived.  The Project Manager will then decide if the seaming will be stopped or postponed.  Such decisions may be the subject of an Action Decision Meeting.

10.3.5 Overlapping and Temporary Bonding

The CQA Consultant will verify that:

  • the  panels  of  geomembrane  have an overlap of approximately 100 mm, sufficient to allow peel tests to be performed on the inner track of the seam;
  • there is a free flap at the edge of the top geomembrane  a minimum of approximately 10 mm wide, to allow a peel test to be performed on the outer track of the seam;
It may be necessary to carefully remove this top flap to prevent ice attaching to it.
  • no solvent or adhesive is used unless the product is approved in writing by the Project Manager (samples must be submitted to the Owner for testing and evaluation);
  • any procedure used to temporarily bond adjacent panels together does not damage the geomembrane.  In particular, the temperature of hot air at the nozzle of any spot seaming apparatus will be controlled such that the geomembrane is not damaged. "Damage" includes a loss in durability; and
Spot "tack" welds at low ambient temperatures have been seen to initiate stress cracks around the heated area. It is preferable that tack welding not be done.
  • temporary bonds do not interfere with the ability to perform shear and peel tests on the actual production seam.

The CQA Consultant will log all relevant temperatures and conditions, and will log and report any non-compliance to the Project Manager.

If protective layers of geomembrane are placed on the barrier layer geomembrane for any purpose (e.g. puncture protection in drainage trenches), they shall not be tack or spot welded to the barrier layer.  They shall be fully welded, except a small pressure relief segment, along the complete periphery of the protective layer or they shall not be welded at all.

Differential contraction effects have caused several barrier layers to be torn at tack welds holding protective layers in place. Sacrificial geomembrane layers will interfere with the ability to locate leaks in the liner by geoelectric methods should such testing be ultimately required.  It is far preferable to use geotextile for protection purposes.

10.3.6 Trial Seams

Trial seams will be made by each machine/operator combination on strips of HDPE geomembrane to verify that  seaming can be successfully performed.  Such trial seams will be made at the beginning of each seaming period (i.e., at the beginning and middle of each working shift), but at least once every four hours, for each seaming apparatus/operator combination used in the seaming period.   In addition, a new trial seam will be conducted when a welding apparatus has been restarted after being switched off.  A trial seam will also be made in the event that the geomembrane temperature changes more than 25°C since the last passing trial seam.  Trial seams will be made under the same conditions as production seams will be made.  When geomembrane temperatures are below 5°C or higher than 75°C more frequent trial seams may be required.  In general, trial seams will be conducted as follows:

The trial seam sample will be at least 1.5 m long by 0.3 m wide with the seam centered lengthwise.  Seam overlap will be as indicated in Section 10.3.5.  The CQA Consultant will observe all trial seam procedures.

Four specimens, each 25 mm wide and a minimum of 150 mm long, will be cut from the center section of the trial seam sample by the Installer.  Two specimens will be tested in shear and two in peel using a calibrated field tensiometer.  They should meet project specifications.  If any specimen fails, the entire operation will be repeated.  If the second trial seam fails, the seaming apparatus and seamer will not be approved for production seaming until the deficiencies are corrected and two consecutive successful trial seams are achieved. The remainder of the successful trial seam sample will be assigned a number and marked accordingly by the CQA Consultant, who will also log the date, time, geomembrane temperature, number of seaming unit, settings, name of seamer, and pass or fail description.

The remainder of the sample will be cut into two pieces, one each to be retained by the Owner, and Installer.

A trial seam shall also be prepared by each seaming machine/operator at the completion of seaming each day to determine whether changes in seam quality might have occurred during the last part of the seaming period.

Alternatively, a seam destructive sample could be required at the end of the day.

10.3.7 General Seaming Procedure

Unless otherwise specified, the general seaming procedure used by the Installer will be as follows:

  • For fusion seaming, a movable protective layer of plastic may be placed directly below each overlap of geomembrane that is to be seamed.  This is to help prevent any moisture build-up between the sheets to be seamed;
  • If required, a firm substrate may be provided by using a flat board, or other similar hard surface placed directly under the seam overlap;
  • Fishmouths or wrinkles at the seam overlaps will be cut along the peak of the wrinkle in order to achieve a flat overlap.  The cut fishmouths or wrinkles will be seamed and any portion where the overlap is inadequate will then be patched with an oval or round patch of the same geomembrane material extending a minimum of 150 mm beyond the cut in all directions.  The end of the cut should be rounded;
  • If seaming operations are carried out at night, adequate illumination will be provided;
  • Seaming will extend to the outside edge of panels placed in the anchor trench.

Each seam will be labelled with the seaming machine number, the operator's initials, machine temperature and speed settings, date, time, and direction seamed. The CQA Consultant will monitor the above seaming procedures, and will inform the Project Manager of any unsatisfactory deviations from standard practice.

10.3.8       Nondestructive Seam Continuity Testing

10.3.8.1 Concept

The Installer will nondestructively test all field seams over their full length using a vacuum test unit, air pressure test (for double fusion seams only), spark test, or other approved method.  Vacuum testing, air pressure testing, and spark testing are described in Sections 10.3.8.3, 10.3.8.4, and 10.3.8.5 respectively).  The purpose of nondestructive testing is to check the continuity of seams.  It does not provide any information on seam strength.  Continuity testing will be carried out as the seaming work progresses, not at the completion of all field seaming.  Nondestructive testing will not be permitted unless there is, in the opinion of the CQA Consultant, adequate illumination.

The CQA Consultant will:

  • observe all nondestructive testing;
  • record location, date, test unit number, operator, and outcome of all testing; and
  • log and inform the Installer and Project Manager of any required repairs.
  • The Installer  will complete  any  required  repairs in  accordance with Section 10.4.

The CQA Consultant will:

  • observe the repair and re-testing of the repair;
  • mark on the geomembrane that the repair has been successfully made and tested;  and
  • document the results.

The following procedures will apply to segments of seams that cannot be nondestructively tested:

  • All such seam segments will be cap-stripped with the same type of geomembrane material, or
  • All such seam segments will be very carefully prepared and welded by the master seamer under the observation of the consultant.
  • If the seam is accessible to testing equipment prior to final installation (e.g. after prefabrication), the seam will be nondestructively tested prior to  final installation.

    For instance, prefabricated pipe boot seams can be tested hydrostatically.

  • The seaming and cap-stripping operations must be observed for proper procedures by the CQA Consultant and Installer's QC representative.
    All extrusion seams can be spark tested if a conductive wire is installed at the triple point of the seam (under edge of top sheet) and grounded prior to seaming.

    The installer will write the details of each seam nondestructive test on the geomembrane.  For air pressure tests this will include the initials of the tester, the date, start time and pressure, end time and pressure, and pass or fail result.  For vacuum testing this will include the initials of the tester, the date, and pass or fail result. For spark testing this will include the initials of the tester, the date, voltage setting, and pass or fail result.  When a test fails, the number of the appropriate repair will also be recorded on the geomembrane.

    10.3.8.2 Submittals

    Prior to any nondestructive testing, the Installer shall submit to the Owner and CQA Consultant calibration certificates for all pressure gages to be used during vacuum and air pressure testing, or shall otherwise demonstrate that all gages are in satisfactory working condition.

    10.3.8.3 Vacuum Box Testing

    The equipment will be comprised of the following:

    • a vacuum box assembly consisting of a rigid housing, a transparent viewing window, a soft neoprene gasket attached to the bottom, port hole, valve assembly, and a vacuum gauge;
    • a vacuum tank and pump assembly equipped with a pressure controller and pipe connections;
    • a pressure/vacuum hose with fittings and connections;
    • a soapy solution that does not cause environmental stress cracking in the geomembrane, and
    • a soap solution applicator.

    The following procedure will be followed:

    • for fusion seams (not normally tested with a vacuum box), cut off the free flap with an approved cutter (so that the lower geomembrane is not damaged) prior to testing the seam;
    • energize the vacuum pump and reduce the tank pressure to approximately 5 kPa gauge;
    • with a soapy solution, wet a strip of geomembrane which is wider and longer than the vacuum box;
    • place the box over the wetted area;
    • close the pressure relief valve and open the vacuum valve;
    • ensure that a leak-tight seal is created;
    • examine the geomembrane seam through the  viewing window for the presence of soap bubbles (large bubbles, or fine froth) for a period of not less than 5 seconds;
    • if no bubbles or foam appear after 5 seconds, close the vacuum valve and open the pressure relief valve.  Move the box over to the adjoining section of seam, with some overlap, and repeat the process;
    • all areas where soap bubbles appear will be marked and repaired in accordance with Section 10.4.3; and
    • excess soap solution shall be cleaned or rinsed off the geomembrane and seam.

    10.3.8.4 Air Pressure Testing

    The following  procedures are  applicable to those seaming processes which produce a double track seam with a central channel. The equipment will be comprised of the following:

    • an air pump equipped with a pressure gauge capable of generating and sustaining a pressure between 160 and 280 kPa mounted on a cushion to protect the geomembrane;
    • a pressure hose with fittings and connections;
    • a sharp hollow needle, or other approved pressure-feed device attached to a pressure gage; and
    • clamps or other devices to seal the ends of the seam to be tested.
    • The following procedures will be followed:
    • seal both ends of the seam to be tested;
    • insert the pressure-feed device into the channel of the seam;
    • energize the air pump to a pressure between 165 and 275 kPa (depending on geomembrane thickness) as indicated in Table 2, close the valve, and allow the temperature of the air in the channel, and thus the pressure, to stabilize for about 2 minutes;

    TABLE 2. AIR CHANNEL TEST PRESSURES FOR HDPE GEOMEMBRANES

      Geomembrane Thickness Minimum Pressure Maximum Pressure
      (mm) (in.) (kPa) (psi) (kPa) (psi)
      1.0 0.040 165 24 240 35
      1.5 0.060 185 27 275 40
      ³2.0  ³0.080 205 30 275 40
    • verify that the stabilized pressure is within the required range and note the pressure loss after a further 5 minutes.  If loss of pressure exceeds the amount indicated in Table 3, or if the pressure does not stabilize, locate the faulty area and repair it in accordance with Section 10.4.3;

    TABLE 3. ALLOWABLE PRESSURE LOSS IN AIR CHANNEL TEST

      Geomembrane Thickness Maximum Pressure Drop
      (mm) (in.) (kPa) (psi)
      1 0.040 28 4.0
      1/5 0.060 21 3.0
      ³2.0 ³0.080 14 2.0
    • verify that the full length of the seam section has been tested by observing the air pressure gauge for a decrease in pressure when the seal at the end of the channel away from the air pump is removed.  If there is a blockage in the channel, the entire seam must be capped, with cap seams being nondestructively tested, or the location of the blockage must be found and the untested part of the seam must be properly tested; and
    • remove the needle or other approved pressure-feed device and seal the hole.
    • Note that a decrease in the geomembrane temperature (e.g. due to clouds) will also cause a reduction in air channel pressure.

        It can be quite difficult to achieve a seal around a needle at low geomembrane temperatures.  Installers use many different techniques to achieve a proper seal.  

    10.3.8.5 Spark Testing

    Spark Testing performed according to ASTM D6365 is frequently used on short, detail (sump, penetration) extrusion welds that cannot be tested by vacuum box testing.   Occasionally it is used on long extrusion seams as the primary nondestructive test method.  The same general test method can also be applied to the geomembrane panels themselves when they are manufactured with an electrically conductive bottom surface layer.

    For seams, a copper wire or tape is placed within the geomembrane overlap, just to the inside of the center of the extruded bead.   The wire is exposed at one end of the seam or it is buried in the conductive subgrade.

    Prior to testing, a trial calibration seam must be made to confirm the minimum voltage required to discharge across a hole in the seam between the search electrode and the copper wire.

    The test procedure is as follows:

    • Connect the negative (ground) electrode of the testing equipment to the end of the copper wire, or to a grounding rod if the copper wire is buried in the subgrade;
    • Connect the positive electrode to the wire brush or other type of search electrode;
    • Clean all debris and moisture from the seam area;
    • Apply a potential difference of between 20 and 55 kVDC, as determined in the calibration test, between the electrodes.  ASTM D6365 recommends the following equation to determine the required potential difference:

    • V= _______
      where: ________   
       
      ________ :

    • Sweep the wire brush electrode over the surface of the seam, maintaining contact with the extruded bead and the top of the lower geomembrane at the edge of the bead;
    • Monitor for audible and/or visible spark discharges that are indicative of a defect.  Mark defects for repair.Care must be taken when spark testing almost completed landfill caps - a spark can cause a small landfill gas explosion. Spark testing must not be performed when the liner is wet.

    • It should be recognized that this test requires no signal be generated for a passing result.  There are many conditions in addition to adequate seaming under which no signal will be generated: proper connections may not be made, the voltage may be set too low, the search electrode may be held too far away.

    10.3.8.6 Visual Examination

    Air pressure, vacuum box, and spark testing methods apply only to seams.  Installer and CQA personnel shall continuously visually examine the geomembrane panels for the presence of other penetrating and nonpenetrating defects and shall continuously feel for protuberances when walking on the geomembrane.

    Visual examination should take advantage of low angles of sunlight and early morning condensation on the geomembrane.

    It may be appropriate to require an electrical method of testing the complete geomembrane for holes, not just the seams as required above.  There are several mobile and in-situ systems that can identify and locate leaks in soil-covered, water covered, and uncovered liners.  In-situ systems monitor the liner integrity very quickly and quickly confirm when repairs have successfully been made.  It is better to perform this test when the cover soil has been placed on the geomembrane, to identify damage caused by the soil's placement.  Infrared thermography can assess seam bond strength nondestructively - particularly useful for difficult tie-in seams.

10.3.9 Destructive Testing

10.3.9.1 Concept

Destructive seam tests will be performed at selected locations.  The purpose of these tests is to evaluate seam bond strength and the effects of seaming on the adjacent geomembrane.  Seam strength testing will be done as the seaming work progresses, not at the completion of seaming.

10.3.9.2 Location and Frequency

The CQA Site Superintendent will select locations where seam samples will be cut out for laboratory testing.  Those locations will be established as follows:

  • A minimum frequency of one sample for every 150 m of seam made by each extrusion machine/operator combination and each fusion machine each day - unless a different frequency is stated in the project specifications.
  • Conditions under which testing frequency may be increased or decreased as the project progresses will be agreed upon by the  Installer, Project Manager, and CQA Manager at the Resolution or Preconstruction Meeting.
Such a method may be the Method of Attributes as published in GRI GM14 (Koerner).
  • Test locations will be determined during seaming at the CQA Site Superintendent's discretion.  Selection of such locations may be prompted by suspicion of overheating, contamination, offset seams, or any other evidence of imperfect seaming;
  • If trial seams are not made at the end of the day one sample for destructive testing shall be removed from the last seam made by each seaming machine at the end of each working day.

The Installer will not be informed in advance of the locations where the seam samples will be taken.

Test frequencies may be increased or decreased at the CQA Site Superintendent's discretion depending on the consistency of the test results.

In critical installations it may be appropriate to take seams from the anchor trench or other strategic (non-critical) locations.  However, this will not randomly spot check the quality of the seamer's work product.

10.3.9.3 Sampling Procedure

Samples will be cut by the Installer as the seaming progresses in order to have laboratory test results before the geomembrane is covered by another material. 

The CQA Consultant will:

  • observe sample cutting;
  • assign a number to each sample, and mark it accordingly; and
  • record the sample location on the layout drawing.

All holes in the geomembrane resulting from destructive sample removal will be immediately  repaired in  accordance  with repair procedures described in Section 10.4.3. The continuity of the new seams in the repaired area will be tested according to Section 10.3.8.

10.3.9.4 Size of Samples

At a given sampling location, two types of samples will be taken by the Installer.

First, two pairs of specimens for field peel and shear testing will be taken.  Each of these specimens will be 25 mm wide by at least 150 mm long, with the seam centered across the width.

The distance between these two pairs of specimens will be 1.1 m.  If both pairs of specimens pass the field tests described in Section 10.3.9.5, a sample for laboratory testing will be taken. The sample for laboratory testing will be located between the two pairs of specimens taken for field testing.  Unless determined otherwise at the Preconstruction Meeting, or in the Project Specifications, the destructive sample will be 0.3 m wide by 1.1 m long with the seam centered lengthwise. 

The sample will be cut into three parts and distributed as follows:

  • one portion, measuring 0.3 m x 0.3 m, to the Installer for QC laboratory testing;
  • one portion, measuring 0.3 m x 0.3 m, to the Owner for archive storage; and
  • one portion, measuring 0.3 m x 0.5 m, to the CQA Consultant for CQA Laboratory testing.

10.3.9.5 Field Testing

The four 25 mm wide specimens mentioned in Section 10.3.9.4 will be tested in the field, by calibrated gaged tensiometer, one of each pair in peel and one in shear.  If any field test specimen fails to pass the criteria of Table 4 and the project specifications, then the procedures outlined in Section 10.3.9.9 will be followed.

The CQA Consultant will witness all field tests and mark all samples and portions with their unique sample number.  The CQA Consultant will also log the date and time of sampling, and test pass or fail description.

If the two pairs of  specimens meet the project specifications, the sample qualifies for testing in the laboratory; if they fail, the seam should be repaired in accordance with section 10.4.3.

10.3.9.6 Construction Quality Assurance Laboratory Testing

Destructive test samples will be packaged and shipped to the CQA laboratory by the CQA Consultant, in a manner which will not damage the test sample.  The Project Manager will verify that packaging and shipping conditions are acceptable.  The Project Manager will be responsible for storing the archive samples.  This procedure will be fully outlined at the Resolution Meeting.  Test samples will be tested by the CQA Laboratory.

Testing will follow ASTM D4437 as modified in NSF 54 Appendix A (1993), but with no requirement for sample conditioning time.  The minimum acceptable values to be obtained in these tests are those indicated in the specifications or as shown in Table 4.  Five specimens will be tested in peel and five in shear.  Specimens will be selected alternately by test from the samples (e.g., peel, shear, peel, shear, etc.).

The CQA Laboratory will provide test results no more than 6 hours after they receive the samples.  The CQA Site Superintendent will review laboratory test results as soon as they become available, and make appropriate recommendations to the Project Manager.

10.3.9.7 Installer's Laboratory Testing

The Installer's laboratory test results will be available to the Project Manager and the CQA Consultant for review.

10.3.9.8 Destructive Sample Pass/Fail Criteria

The criteria shown in Table 4, or the requirements of the project specifications (whichever are the more comprehensive) must be met for the acceptance of peel and shear test specimens:

TABLE 4. SEAM SPECIMEN TEST (ASTM D4437) SPECIFICATIONS

PARAMETERS CRITERIA
Peel Strength
Fusion seam  >  70%
Extrusion seam  > 65%
Minimum specified* geomembrane yield strength
Seam Separation
Zero
Shear Strength
> 95% minimum specified* geomembrane yield strength
Elongation
> 100% of distance between edge of seam and nearer grip
Location of Failure
Outside the weld

* The yield strength specified by the Manufacturer, which is usually the population average value less 2 standard deviations.

There is, in fact, little technical significance to the determination of seam shear strength and peel strength due to the large area of the shear interface.  The seam bond strength will have to be less than about 20% of maximum bond strength for the seam to fail before the geomembrane breaks.  However, these strength parameters are retained in the seam specifications since regulators will likely not accept specifications without them.

The inclusion of seam peel separation and shear elongation parameters provides some indication of the durability of the seam.   Shear elongation indicates if damage to the geomembrane has occurred during seaming. This is extremely important. If seam separation can occur during the application of peel stresses (as can occur in the field) there may be a decrease in stress rupture resistance of the geomembrane.

The peel criteria apply to both tracks of double track seams.  Nine out of the ten specimens in a seam destructive sample must meet the criteria above for acceptance of the complete destructive sample.

Other sample acceptance criteria allow 1 peel and 1 shear specimen failure, but not 2 peel, or 2 shear failures.  Alternatively, 1 failure is allowed (for each of peel and shear) provided the average values of all five specimens meet the strength criterion.  However, the failing specimen must exceed 80% of the specified strength.  Note that it is not difficult for good installers to make seams in which all the specimens pass, and good installers will require 10 passing specimens in their QC programs.

The CQA Consultant will ensure that the CQA Laboratory retains all sample and specimen remnants, clearly labelled, for at least 30 days after the last specimen for the project has been tested.

10.3.9.9 Procedures if Destructive Sample Fails

The following procedures will apply whenever a sample fails a destructive test, whether that test is conducted by the CQA Laboratory, the Installer's laboratory, or on the field tensiometer. 

The Installer has two options:

  • Reconstruct the seam between the nearest passing destructive test locations on each side of the failed sample; or
  • Trace the seaming path to an intermediate location (3 m minimum from the failed test location in each direction) and take a small sample for an additional field test at each location. If these additional samples pass tensiometer testing, then full destructive test samples should be taken.  If these laboratory destructive test samples pass the tests, then the seam should be reconstructed between these locations by capping.  If either sample fails, then the process is repeated to establish the zone in which the seam should be reconstructed.

If a fusion-type seam fails destructive testing and the Installer chooses to repair the seam, the only acceptable repair method is as described in Section 10.4.3.  Applying topping (bead of extrudate) is not an approved method of capping any seam unless it can be shown that this procedure will not reduce the stress rupture resistance of the seam below 75% of that of the parent geomembrane.

It is not acceptable to trim off the free flap and to apply an extrusion bead along the edge of the outer fusion track.  This will result in a double heating and perhaps overheating of the geomembrane adjacent to the original seam.  Extrusion beading over the free flap may be acceptable if the free flap exceeds 20 mm in width so that the heat affected zone of the extrusion bead does not overlap the heat affected zone of the outer track of the original seam.

Only seams bounded by two locations from which samples passing laboratory destructive tests have been taken will be considered acceptable. An additional destructive test sample will be taken from repair seams when the length of a reconstructed seam exceeds 50 m.  This sample must pass destructive testing or the procedure outlined in this section must be repeated. The CQA Co