|
Title: Specification,
CQA Plan, and Installation Guide for fPP Pond Liners with Geocomposite
Drainage Layer |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
|
1.0 INTRODUCTION This document has been prepared for a 1 mm flexible polypropylene (fPP) liner with a geocomposite drainage and gas venting layer underneath. The fPP geomembrane must be made with Basell CA743GA or CA 721GW natural resin with pre-compounded antioxidant additives. Carbon (N110) content should be nominally 2.75% but must be between 2.5 and 3.25%. Additional additives added by the geomembrane manufacturer to improve UV and thermal resistance of the geomembrane are allowed but they must be generically identified and it should be demonstrated to the Project Engineer using test data that improvements are achieved. The geomembrane will be underlain by a double-sided geotextile/geonet composite (geocomposite) for both leakage collection/drainage, and for trapped air and biogas venting. At operating head the maximum allowable leakage flow rate shall be 100 gpad (1000 lphd). Leakage shall be recirculated into the pond. The following specifications, installation guidelines, and CQA Plan should clarify to all parties the requirements of the Owner, so that all parties are on a level playing field. If there are any concerns they should be addressed to the Owner or Project Engineer for resolution before the installation starts. 2.0 PARTIES INVOLVED 2.1 Geomembrane Manufacturer The Manufacturer shall be able to provide sufficient production capacity and qualified personnel to meet the demands of the project. The Manufacturer shall be pre-qualified and approved by the Engineer and the Owner. The qualifications presented by the Manufacturer will, as a minimum, include: • Corporate background and information • Manufacturing capabilities: • A list of at least 5 completed projects (and contacts) totaling a minimum area of 1,000,000 m2, for which the Manufacturer has manufactured PP geomembrane materials from the same type of PP resin as that proposed to be used for this project. 2.2 Geomembrane Fabricator The Fabricator shall meet the same requirements as the manufacturer. 2.3 Geomembrane Installer The Installer will be trained and qualified to install PP geomembranes. The Installer will be approved and/or licensed by the Manufacturer. A copy of the approval letter or license will be submitted by the Installer to the Project Manager. Prior to confirmation of any contractual agreements, the Geomembrane Installer will provide the Project Manager with the following written information: • Corporate background and information • Installation capabilities: . information on equipment and personnel, • A list of at least 5 completed facilities (and contacts) totaling a minimum area of 500,000 m2, for which the Installer has installed PP geomembrane All personnel performing seaming operations will be qualified by experience. At least one seamer per crew will have experience seaming a minimum of 50,000 m of seams using the same method of seaming proposed for use on this project. The most experienced seamer, the "Master Seamer", will provide direct supervision, as required, over less experienced seamers. The Master Seamer, or his designate with equivalent experience, will be on site whenever seaming is being performed. The Installer will provide the Project Manager with a list of proposed seaming personnel and their professional records. This document will be reviewed by the Project Manager and the CQA Consultant. Any proposed seaming personnel deemed insufficiently experienced will not be accepted by the Project Manager or will be requested to pass a seaming test. The Installer will designate one representative as his Site Supervisor who will represent the Installer at all site meetings and be responsible for acting as the Installer's spokesman on site. The Supervisor will be qualified by experience. The Supervisor must have supervised the installation of a minimum of 300,000 m2 of PP geomembrane. He will also exhibit good management and communications skills. His appointment will be approved by the Project Manager. The Installer will also designate one representative with responsibility for Quality Control and signing all QC documents. 2.4 Transporter All personnel responsible for the loading, transporting, and unloading of the PP geosynthetics must be fully aware of the consequences of damage to the materials, and must be familiar with handling and transportation constraints required by the Manufacturer. The Transporter will ensure that all rolls are shipped on trailers that can be accessed from the side for safe unloading. The decks of the trailers shall be visually inspected for exposed nails by the Manufacturer before loading. Any such nails shall be removed. 2.5 Construction Quality Assurance Consultant The CQA Consultant will be experienced with PP geomembranes and be knowledgeable of PP geomembrane and seam performance characteristics. The CQA Consultant will be experienced in the preparation of CQA documentation including CQA manuals, forms, reports, and certifications. The CQA Consultant will provide the following, in writing, to the Owner: • Corporate background and information. • A summary of the firm's experience in CQA of PP geomembranes, including a list of at least 3 completed facilities (and contacts) totalling a minimum of 100,000 m2 in area, for which the CQA Consultant has provided CQA services. • CQA forms used by the firm, • Quality control manual or a summary of quality control practices. 2.6 Construction Quality Assurance Laboratory The CQA Laboratory will have experience in testing PP geomembranes and seams and be familiar with ASTM, GRI, and other applicable test standards. The CQA Laboratory will be capable of providing test results within 6 hours of receipt of seam samples and will maintain that standard throughout the project. The laboratory shall be accredited by GAI-LAP (or other national accreditation organization) for those tests included in the Project Specifications and this CQA Plan. The CQA Laboratory shall be approved by the CQA Consultant and the Owner/Project Manager. 2.7 Duties of Construction Quality Assurance Personnel The personnel of the CQA Consultant include: • The CQA Manager, who operates from the office of the CQA Consultant and visits the site as required; • The CQA Site Superintendent, who is located at the site; and • The CQA Monitor(s), if any, who is (are) located at the site. The duties of the CQA Personnel are discussed in the following subsections. 2.8 CQA Manager The CQA Manager: • reviews all designs, plans, specifications, QC programs, and the CQA Plan; • reviews all other site-specific documentation, including bid documents, proposed panel layouts, and the geomembrane manufacturer and installer literature, for correctness, constructibility, level of quality and potential conflicts. • attends the preconstruction meeting; • ensures that the Manufacturer and Installer have reviewed, and can comply with, the Project Specifications and the CQA Plan; • administers the CQA program, i.e., assigns and manages all CQA personnel, reviews all field reports, and provides engineering review of all CQA-related issues; • provides quality control of the CQA personnel, including making site visits; • reviews all changes to the design, plans, specifications, and installation procedures; • proactively recommends quality improvements to the Project Manager within project budget constraints; and • with the CQA Site Superintendent, reviews the record drawings and prepares the final report. 2.9 CQA Site Superintendent The CQA Site Superintendent: • acts as the on-site (resident) representative of the CQA Consultant; • familiarizes all CQA Monitors with the site, the CQA requirements, and health and safety requirements for the project; • manages the daily activities of the CQA Monitor(s); • attends all CQA-related meetings (e.g., Resolution, Preconstruction, daily, weekly); • verifies the calibration and condition of on-site testing equipment; • reviews all CQA Monitors' daily reports and logs; • reports to the Project Manager, and logs in his daily report, any relevant observations reported to him by the CQA Monitors; • prepares his/her own daily report; • assigns locations for testing and sampling; • oversees the collection and shipping of all laboratory test samples; • reviews results of laboratory testing
and makes appropriate recommendations; • prepares or oversees the ongoing preparation of the Record Drawings; and • assists with the preparation of the final report. The CQA Site Superintendent also: • reviews all Supplier, Manufacturer, and Installer certifications and documentation, and makes appropriate recommendations; • reviews the Installer's personnel qualifications for conformance with those pre-approved for work on-site; • ensures that the Manufacturer and Installer have reviewed and can comply with the Project Specifications and the CQA Plan. • notes, and reports to the Project Manager, any on-site activities that could result in damage to the geomembranes and other geosynthetics. • makes recommendations for improvements
in the liner quality; and
All formal communications between the CQA Consultant and Owner will be in writing between the CQA Manager and the Project Manager. The CQA Site Superintendent may initiate such communications but they will eventually require the CQA Manager's signature. The CQA Site Superintendent is expected to maintain informal communications with other on-site staff of project parties but will not issue direct instructions to them. The CQA Site Superintendent, with the CQA Manager's approval, will present CQA team proposals and supporting arguments to the Project Manager who will make the final decisions. All formal communications between parties to the project will pass
through the Project Manager unless otherwise approved by the Project
Manager. Under no circumstance will CQA staff or any other project party disclose project related information to strangers on the site. It is recommended that the Owner issue distinctive badges to all project personnel in order that strangers can be identified. Speed and permanent records will be the essence of all communications.
In this CQA Plan, all properties and dimensions are expressed in SI units. If the manufacturer, fabricator, or installer presents information or data in US units, the SI units in this plan shall be deemed to govern. It should be noted that the conversion is typically only accurate to within ten percent (10%).
5.1 Project Coordination Meetings To guarantee high quality and smooth workflow during installation, clear, open channels of communication are essential. To that end, meetings are critical. 5.1.1 Resolution Meeting Following the completion of the design, plans, specifications, and this CQA Plan for the project, a Resolution meeting will be held. This meeting will include all parties then involved, including the CQA Manager, the Project Manager, the Engineer, the General Contractor, and the Installer. The purpose of this meeting is to begin planning for coordination of tasks, to anticipate any problems which might cause difficulties and delays in construction, and, above all, to present the CQA Plan to all of the parties involved. It is very important that the procedures regarding testing, repair, etc., be known and accepted by all. This site specific CQA Plan may be amended at the Resolution Meeting, after review by the CQA Consultant. The first part of the Resolution Meeting may be devoted to a review of the design drawings and specifications. This is different from the peer review of the design, including design calculations, which would have been carried out previously. This meeting should include all of the following activities: • review critical design details of the project; • review the Project Specifications; • review the CQA Plan; • review the Manufacturer's and Installer's QC Programs for compatibility with other project documents. • review the panel layout drawing; • make appropriate modifications to the CQA Plan to ensure that it identifies all necessary CQA; • make appropriate modifications to documents to ensure their integration and compatibility; • reach a consensus on the CQA and quality control procedures, especially on methods of determining acceptability of the PP geomembrane; • assign the responsibilities of each party; • decide the number of geomembrane seaming units to be maintained on-site by the Installer (this number depends on the number of seaming crews and on the type of seaming equipment); • establish work area security and health and safety protocols; • confirm location of nearest medical centre, hospital, and police station; • confirm the methods for documenting and reporting data, and for distributing documents and reports; and • confirm the lines of authority and communication. The meeting will be chaired by the Project Manager and will be documented by a person designated at the beginning of the meeting, or by the CQA Consultant. Minutes will be transmitted to all parties by fax or email within 48 hours, and will be edited and returned to the Project Manager within a further 24 hours. 5.1.2 Pre-Construction Meeting A Pre-Construction Meeting will be held at the site. At a minimum, the meeting will be attended by the Project Manager, the CQA Site Superintendent, the General Contractor, and the Installer. The meeting will be chaired by the Project Manager or designate. Specific requirements for this meeting are to: • make any final modifications to the CQA Plan; • review the project specifications; • review the responsibilities of each party; • review and confirm lines of authority and communication; • review methods, forms and routing for documents and reports; • establish protocols for sampling and testing; • establish protocols for handling deficiencies, repairs, and retesting; • review the schedule for all operations; • establish rules for writing on the geomembrane, i.e., who is authorized to write, what can be written, and in which color; • outline procedures for packaging and storing archive samples; • review panel layout and numbering systems for panels and seams; • establish procedures for use of the seaming equipment; • finalize field cut-out sample sizes; • review qualifications of CQA Independent Laboratory; • review repair procedures; • review procedures for compensation allowance, treatment of wrinkles, and obtaining intimate contact between geomembrane and subgrade; • review activities and responsibilities associated with maintaining, dewatering, and filling the anchor trench; • consider environmental problems that could occur (excessive wind, rain etc.) and associated remedial activities; • conduct a site walk-around to verify that earthwork construction is proceeding on schedule, and to review material storage locations, and The meeting will be chaired by the Project Manager and will be documented by a person designated at the beginning of the meeting. Minutes will be transmitted to all parties within 24 hours, for approval and signature within a further 24 hours. 5.1.3 Progress Meetings A weekly progress meeting will be held between the Project Manager and the CQA Site Superintendent, the Installer, the General Contractor, and any other concerned parties. The meeting will be chaired by the Project Manager or designate. Minutes will be recorded by the Project Manager or designate. This meeting will discuss current progress, planned activities, revisions to the work, and any new business. The CQA Site Superintendent will log any problems, decisions, or questions arising at this meeting in his/her daily reports. Any matter requiring action which is raised in this meeting will be reported to the appropriate parties. Minutes of the meeting will be circulated to all parties within 24 hours. Corrections must be made and submitted to the Project Manager within a further 24 hours. 5.1.4 Action Decision Meeting This special meeting will be held when, and if, a problem or deficiency has occurred, or is likely to occur, that requires special action decisions by several parties. The meeting will be attended by the Project Manager, the CQA Site Superintendent, the Installer and other involved parties. If the problem requires a design modification, the Design Engineer should also be present. The purpose of the meeting is to define and resolve the problem or work deficiency as follows: • Define the problem or deficiency; • Establish the cause; • Define possible solutions; • Select a suitable technical solution agreeable to all parties • Define an action plan to implement the solution; and • Identify the party responsible for implementing the solution. The meeting will be chaired by the Project Manager and documented by a person designated at the meeting. Minutes will be transmitted to affected parties within 24 hours. Corrections must be made and submitted to the Project Manager within a further 24 hours. 5.2 Project Control Visits Periodically, the construction site may be visited by the CQA Manager. This visit should, if necessary, be coordinated with a similar visit by the Project Manager.
6.1 Polypropylene Geomembrane Manufacturing The fPP geomembrane must be made with Basell CA743GA or CA721GW PP natural resin with antioxidant additives. Carbon (N110) content should be nominally 2.75% but must be between 2.5 and 3.0%. Additional additives added by the geomembrane manufacturer to improve UV and thermal resistance of the geomembrane are allowed but they must be identified and it should be demonstrated to the Project engineer using test results that improvements are achieved. Geomembrane rolls may be prefabricated into larger panels to minimize field seaming. 6.1.1 Raw Material The raw material will be first quality PP resin containing no more than 5% clean post-industrial (edge trim) recycled polymer by weight. Quality Control Certificates will be provided for all resin used to manufacture the geomembrane. 6.2 Quality Control The Manufacturer and Fabricator shall make available to the Owner and CQA Consultant Manufacturing Quality Control manuals which outline all quality procedures which will be implemented for the manufacture of the PP geomembranes. 6.3 Manufacturing 6.3.1 Submittals Prior to the installation of any geomembrane, the Manufacturer will provide the Project Manager and the CQA Consultant with the following: • A certified properties sheet including, at a minimum, all specified properties, and test methods indicated in the specifications; • A list of quantities and descriptions of materials other than the base polymer which comprise the geomembrane; and • The internal MQC sampling procedures, frequencies of testing, and results of testing of material supplied to the project. The CQA Consultant will verify that: • the property values certified by the Manufacturer meet all of the Manufacturer's specifications; and • the measurements of properties by the Manufacturer are properly documented, the test methods used are acceptable, and the geomembrane meets the Project Specifications. 6.3.2 Rolls Prior to shipment, the Manufacturer will provide the Project Manager and the CQA Consultant with Quality Control certificates covering each roll of geomembrane and welding rod provided. The Quality Control certificate will be signed by a responsible party employed by the Manufacturer, preferably the QC Laboratory Manager. The Quality Control certificates will include: • resin Manufacturer, resin type, resin lot number, and geomembrane roll numbers; and • results of Quality Control tests. At a minimum, results will be given for thickness, specific gravity/density, uniaxial tensile strength and elongation at break and carbon black content and dispersion, evaluated in accordance with the methods indicated in the specifications or equivalent methods previously approved by the Project Manager and CQA Consultant. No material will be installed until complete QC test data have been provided. The CQA Consultant will: • verify that the Quality Control certificates have been provided at the specified frequency for all rolls, and that each certificate identifies the rolls and resin related to it; and • review the Quality Control certificates and verify that the certified roll properties meet the Manufacturer's and Project Specifications. 6.3.3 Fabrication The geomembrane may be prefabricated under controlled conditions into larger panels to minimize the number of field seams. These panels will be up to approximately 2,500 m2 (25,000 ft2) in area. Each panel will be given an identifying number and a log will be kept of all roll numbers used to fabricate that panel. The seams may be made by dielectric welding equipment or thermal fusion equipment. They may be dual track seams with a center air channel for air pressure testing (see Section 8.3.8.4) or they may be single track seams a minimum of 25 mm wide bonded to the edge of the top sheet. All factory seams will be nondestructively tested along their full length using the air pressure test on the double track seams or the air lance test on single track seams. The air lance shall have a nozzle approximately 4.5 mm in diameter and deliver air to the edge of the seam at a pressure of about 380 kPa (55 psi) from a distance of about 10 mm. On each panel at least one seam will be made a little longer than normal so that a sample can be removed for destructive testing (see Section 8.6). The destructive test sample shall not be made by running separate pieces of material through the welder. Throughout the fabrication process the surfaces of the panels shall be visually examined for flaws and defects. Any such flaws and defects shall be repaired (Section 8.7) before the panel is shipped. The location of each flaw/repair shall be recorded on a repair log and shipped to site with the QC documents for that panel. Any observed flaws/defects that could not be repaired prior to shipping shall clearly be identified on the log. QC certificates for the resin used to make the geomembrane rolls, for the manufacturing of the rolls, and the fabrication of the panels, shall be sent to the Project Engineer before material arrives on site. Panels shall be accordion folded and rolled on a rigid core for shipping. Accordion folding in two directions is not permitted. 6.3.4 General Note on Testing Throughout this project, it is necessary that all non-passing test results be recorded on record logs and data sheets. It must be evident that failures have occurred and the actions required to correct the failures must be identified. 6.3.5 Conformance Testing Conformance testing is not an opportunity to reproduce the QC testing program, but is simply a spot-check to provide confidence that satisfactory material is delivered to the site. 6.3.5.1 In-Plant testing The purpose of in-plant material conformance test sampling is to verify that geomembrane material which is designated for the Owner's project is confirmed as meeting the project specifications prior to shipment to the site. Thus, barring a transportation accident, the geomembrane can be installed immediately it arrives on site. The Manufacturer will make available all necessary personnel and equipment to assist the CQA Consultant in retrieving conformance samples of the geomembrane material. The CQA Consultant shall send to the CQA Laboratory conformance samples for testing as outlined in Section 6.3.6. The frequency of sampling shall be at the discretion of the CQA consultant but shall typically be between each 10,000 and 25,000 m2 of geomembrane. No material shall be shipped to the site until conformance test results are obtained. The CQA Consultant shall report any nonconformance of sampling procedures as outlined in Section 6.3.10 to the Project Manager. 6.3.5.2 On-site material testing If In-Plant conformance testing is not performed, upon delivery of the rolls of geomembrane to the site, the CQA Consultant will ensure that samples are removed at a frequency of at least 1 sample per 10,000 m2 and forwarded to the CQA Laboratory for testing to ensure conformance to both the Project Specifications and the Manufacturer's list of guaranteed properties. 6.3.5.3 Properties of the PP Geomembrane The PP geomembrane shall meet the specifications shown in Table 1. TABLE 1. PP GEOMEMBRANE SPECIFICATIONS
6.3.6 Conformance Tests At a minimum, tests to determine the following parameters will be performed on PP geomembranes: • thickness; • carbon black content and dispersion; and, • uniaxial tensile break strength and elongation. 6.3.7 In-plant conformance sampling In the interests of time, rolls may be sampled in the plant for conformance testing but without the CQA consultant being present. A full roll width sample will be cut out by the manufacturer in a free-hand wavy pattern from the end of a roll and sent to the CQA laboratory for testing. At the conclusion of testing, the remaining sample material will be sent to the site so that the cut edge can be matched to the cut edge on the roll. Assuming passing test results the material can be used as soon as it arrives on site. 6.3.8 Sampling Procedures Samples will be taken across the entire width of the roll and will not include the outer wrap of the roll. Unless otherwise specified, samples will be 500 mm long by the roll width. Specimens for testing will be taken across the full width of the sample. If roll numbers are very different and non-sequential, consideration should be given to testing each block of roll numbers at the same frequency. 6.3.9 Test Results The CQA Consultant will examine all results from laboratory conformance testing and will report any nonconformance to the Project Manager. 6.3.10 Procedures in the Case of a Conformance Test Failure The following procedure will apply whenever a sample fails a conformance test that is conducted by the CQA Laboratory: • The Manufacturer will replace the roll of geomembrane that is in nonconformance with the specifications with a roll that meets specifications. • The CQA Site Superintendent will remove conformance samples for testing by the CQA Laboratory from the next higher and lower numbered rolls. These two samples must both conform to specifications. If either of these samples fail, testing shall continue until the defective rolls are isolated. These rolls will be replaced by the Manufacturer, at no expense to the Owner. This additional conformance testing will be at the expense of the Manufacturer. The CQA Consultant will document actions taken in conjunction with conformance test failures. 6.4 Delivery 6.4.1 Transportation and Handling Transportation of the geomembrane is the responsibility of the Manufacturer, Installer, or other party as agreed upon. All handling on-site is the responsibility of the Installer. The CQA Consultant will verify that: • handling equipment used on the site is adequate and does not pose any risk of damage to the geomembrane particularly to the edges of the geomembrane; and • the Installer's personnel handle the geomembrane with care. Upon delivery at the site, the Installer and the CQA Consultant will conduct a visual examination of all rolls for defects and signs of damage. This examination will be conducted without unrolling rolls unless defects or damage are found or suspected. The CQA Consultant will indicate to the Project Manager: • any rolls, or portions thereof, which should be rejected and removed from the site because they have unacceptable flaws; and • any rolls which contain minor repairable flaws. 6.4.2 Storage The Installer will be responsible for the storage of the geomembrane on-site. The Project Manager will provide storage space in a location (or several locations) such that on-site transportation and handling are minimized. Geomembrane rolls will be stored on a smooth, dry, level surface in an area where the geomembrane, particularly the roll edge, is protected from damage. Rolls, particularly textured rolls, will not be allowed to get dirty. The CQA Consultant will verify that storage of the geomembrane ensures adequate protection against dirt, impact, and other sources of damage. Rolls will not be stored more than 3 high. Access will be provided to each end of stored rolls for the examination of identification labels and examination of roll edges. Chocks to prevent rolling will be bevelled to avoid concentrated stresses on the geomembrane. 7.0 GEOCOMPOSITE The double purpose leakage collection/drainage and gas venting layer shall be a biplanar or triplanar HDPE geonet with a nonwoven geotextile on each side, the upper one for increased friction with the underside of the geomembrane and the lower one to act as filter between the subgrade soil and the drainage layer. Note: In double geomembrane lining systems, if an electrical integrity survey of the primary liner is required the upper geotextile of the geocomposite shall be electrically conductive. 7.1 Specifications and QC certificates The geocomposite and its component parts shall meet the specifications shown in Table 2. The geonet strands shall not contain any fillers or voids. TABLE 2. GEOCOMPOSITE SPECIFICATIONS
(a) Hydraulic Gradient 0.1, normal load 10 kPa Prior to arrival of the geocomposite on-site the Installer shall provide the Project Engineer with signed quality control certificates from the manufacturers of the geotextiles, the geonet, and the fabricated geocomposite. A QC certificate for the HDPE resin used in the geonet shall also be provided. 7.2 Shipping and storage The geocomposite shall be wrapped with untorn impermeable and opaque protective covers on arrival at the site and shall be stored on smooth, dry surfaces, and in such a way that if it rains the geonet will not be contaminated. Rolls will be stored no more than three high. Each roll will be identified, on the cover, with the manufacturer’s name, the product type, the roll number, its width, its length, and its weight. Labels must be readable while the roll is in its stored location. 7.3 Conformance testing One roll every 10,000 m2 will be sampled across the full roll width for conformance testing at an independent GAI-LAP accredited geosynthetics testing laboratory (or other nationally recognized accreditation organization). More rolls may be sampled if roll numbers are not significantly sequential. The following conformance tests will be performed: • Geonet density (ASTM D1505) Failing samples will result in that roll being set aside. The next higher and lower roll numbers will then be tested, and so on until the extent of the non conformance is defined. Any additional testing after the first roll, and costs to replace nonconforming rolls, will be to the account of the Installer. 7.4 Installation Rolls will be handled with equipment that does not damage the geotextile or the geonet. Rolls will be unrolled under controlled conditions (i.e. not allowed to unroll freely down slopes) and deployed material shall not be under stress. Geocomposite will extend completely over all concrete pads at pipe penetrations. A geotextile strip will be placed over all cut edges of geonet to prevent the sharp edges from damaging the overlying geomembrane. Seams will be oriented up and down slopes, not across slopes, and there shall be no seam closer than 3 m (10 ft) to the toe of any slope. Care shall be taken not to contaminate and block the passageways in the geonet with soil. Any such soil shall be removed by the installer to the satisfaction of the CQA Superintendent. Roll edges shall be overlapped about 150 mm (6 in). Butt joints at the ends of rolls shall be overlapped 300 mm (12 in). All roll end joints shall be shingled down slope. The underside geotextiles at the edges of rolls shall be carefully fully overlapped without folding. The sides of the geonet rolls on the floor shall be fastened with plastic ties (not metal ties or staples) every 2 m (6 ft) and every 1 m (3 ft) on side slopes. In the anchor trench the geonet shall be fastened every 500 mm (20 in.). The top geotextiles shall also be fully overlapped and thermally bonded to prevent separation, extending to the edge of the geocomposite in the anchor trench. At roll end overlaps the top geotextile of the bottom roll and the bottom geotextile of the top roll shall be removed to allow continuous drainage across the joint. A strip of geotextile at least 300 mm (12 in.) wide will be placed on the subgrade at the end of the lower roll to prevent soil accessing the end of the geonet. The geonet will be tied with plastic ties at least every 500 mm (20 in.). Where there are two layers of geocomposite it shall be ensured that the strands of one layer do not penetrate the strands of the other layer and cause restrictions to flow. All damaged geonet and geotextile will be repaired with patches of geotextile or geocomposite as appropriate. If damage exceeds half the width of a roll the damaged section of the roll shall be cut out and a full roll width joint made. Such joints will not be allowed on side slopes. Only that amount of geocomposite shall be deployed each day that can be covered with geomembrane. As necessary, geocomposite rolls shall be ballasted with sand bags or other non-damaging weights to prevent displacement during reasonably foreseeable winds. Any exposed edges of geocomposite shall be covered and protected from mechanical damage and infiltration by soil. 7.5 Repairs Repair patches shall overlap the damaged area by at least 500 mm (20 in.) in all directions. Geotextiles between geonet layers shall be removed to allow continuity of flow within the geonet layer. Edges of geonet exposed to soil shall be suitably covered by a layer of geotextile to preclude access of soil. A strip of geotextile will be placed over the edge of cut geonet to protect the underside of the geomembrane from puncturing damage by sharp edges of the geonet. Patches shall be fastened to the base geocomposite with plastic ties every 300 mm (12 in.) around the circumference on the floor of the lake and every 150 mm (6 in.) on the side slopes. Alternatively the two geotextiles shall be heat bonded together to prevent displacement of the patch. When the patch is first attached the top geotextile of the base geocomposite around the patch will be marked to indicate whether the patch has subsequently moved prior to placement of the geomembrane.
8.1.1 Surface Preparation 8.1.2 Anchor Trenches 8.2 Geomembrane Placement 8.2.1 Field Panel Identification 8.2.2 Field Panel Placement 8.2.2.1 Compensation for Material Expansion and Contraction 8.2.2.2 Installation Schedule The CQA Consultant will record the identification code, roll number, location, weather conditions, and date of installation of each field panel. 8.2.2.3 Weather Conditions 8.2.2.4 Geomembrane Placement • geomembrane is not allowed to unroll
freely down a slope; 8.2.2.5 Temporary Ballasting 8.3 Field Seaming Horizontal roll end seams are not allowed on slopes. 8.3.2 Seaming Equipment and Products Fusion seaming must be done with automated self-propelled machines.
The fusion seaming machines will be equipped with gauges giving hot
wedge temperatures. Temperature, speed, and nip roll pressure settings
will be verified by the Installer prior to each seaming period. Nip
roll and wedge geometries shall be such as to minimize residual stresses
at the edge of the seam. • equipment used for seaming does
not damage the geomembrane; 8.3.3 Seam Preparation 8.3.4 Weather Conditions for Seaming If the Installer wishes to use methods which
may allow seaming at geomembrane temperatures above 80°C, the Installer will demonstrate
(by testing trial seams) that such methods produce seams which are
entirely equivalent to seams produced at geomembrane temperatures
below 80°C, and that the overall quality of the seam and durability
of the geomembrane are not adversely affected. In addition, the Installer
will prepare written certification that states that the seaming procedure
does not cause any physical or mechanical modification to the geomembrane
that will generate any short or long-term damage to the geomembrane
liner. 8.3.5 Overlapping and Temporary Bonding A trial seam will also be made in the event
that the geomembrane temperature changes more than 25°C since the last passing trial
seam. Trial seams will be made under the same conditions as production
seams will be made (e.g. on slopes if production seams are to be
made on slopes). When geomembrane temperatures are higher than 80°C
more frequent trial seams may be required. Four specimens, each 25 mm wide and a minimum of 150 mm long, will
be cut from the center section of the trial seam sample by the Installer.
Two specimens will be tested in shear and two in peel using a calibrated
field tensiometer. They should meet project specifications. If any
specimen fails, the entire operation will be repeated. If the second
trial seam fails, the seaming apparatus and seamer will not be approved
for production seaming until the deficiencies are corrected and two
consecutive successful trial seams are achieved. The CQA Consultant will observe all trial seam procedures. 8.3.7 General Seaming Procedure •If required, a firm substrate may be provided by using a flat board, or other similar hard surface placed directly under the seam overlap. • Care shall be taken during extrusion
and hot air seaming that the underlying geotextile is not melted. • If seaming operations are carried
out at night, adequate illumination will be provided. 8.3.8 Nondestructive Seam Continuity Testing The CQA Consultant will: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||